12508 W CALIFA ST 91607
Certificate Information: 12508 W CALIFA ST 91607
- Application / Permit
- 20014-20000-02660
- Plan Check / Job No.
- B20VN08518
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 34'-7" X 14'-8" ADDITION TO THE FRONT OF (E) SFD FOR NEW BEDROOM AND EXTEND ENTRY & 7'0" X 4'-0" ADDITION TO REAR FOR NEW BATHROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/13/2020
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2020 | ROSENDO MEDINA |
| Corrections Issued | 6/29/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 7/30/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/8/2020 | ROSENDO MEDINA |
| Issued | 10/13/2020 | APPLICANT |
| CofO in Progress | 3/4/2024 | JOSE AVILA |
| CofO Issued | 9/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/8/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 9/23/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 9/25/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arsen, Adzhemyan; Lic. No.: C89103 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/19/2021 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 8/2/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/5/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/1/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/1/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 9/1/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 9/3/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/18/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/18/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 1/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/25/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/25/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 1/25/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/25/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 2/1/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/1/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/1/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/14/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 4/14/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/6/2022 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Final | 1/18/2023 | Partial Approval | KIRK SANDERS |
| Final | 4/7/2023 | Partial Approval | KIRK SANDERS |
| Final | 2/23/2024 | Corrections Issued | JOSE AVILA |
| Final | 3/1/2024 | OK to Issue CofO | JOSE AVILA |