541 3/4 N SPAULDING AVE 90036

Certificate Information: 541 3/4 N SPAULDING AVE 90036

Application / Permit
20014-20000-02653
Plan Check / Job No.
B20VN08497
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION TO (E) GARAGE & CONVERAT TO ACCESSORY DWELLING UNIT ( 18'0"x24'-2") per LAMC 12.22 A.33(c)¹, (d)¹, and (g) fire sprinklers NFPA-13D
Permit Issued
Issued on 12/16/2020
Issuing Office
Current Status
CofO Issued on 9/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 MOHAMMAD ESMAILI
Corrections Issued 7/25/2020 MOHAMMAD ESMAILI
Quality Review Completed 8/13/2020 OMID HEDAYAT
Building Plans Picked Up 8/17/2020 APPLICANT
Plan Check Approved 12/14/2020 MOHAMMAD ESMAILI
Issued 12/16/2020 APPLICANT
CofO in Progress 7/9/2021 CHRIS CHRISTENSEN
Permit Finaled 9/4/2021 DEROLD HAUFF
CofO Issued 9/4/2021 DEROLD HAUFF
Permit Finaled 9/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/6/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 10/6/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/8/2020 WALLIE JONG
Sewer availability Cleared 10/8/2020 WALLIE JONG
City Hist. Cultural Monument Cleared 11/5/2020 MICAELA TORRES-GIL
Historic monument Cleared 11/5/2020 MICAELA TORRES-GIL
Historic monument Cleared 11/5/2020 MICAELA TORRES-GIL
Construction near power lines Cleared 11/6/2020 RIDWAN HARDY
Miscellaneous Cleared 12/10/2020 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/21/2020 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 12/21/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 12/21/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 12/21/2020 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 12/24/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 1/27/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 1/28/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/28/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 1/28/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 1/28/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 1/28/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 1/28/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/26/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 2/26/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 2/26/2021 Approved CHRIS CHRISTENSEN
Insulation 3/3/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/3/2021 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 3/8/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/8/2021 Approved CHRIS CHRISTENSEN
Sewer 4/9/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 6/2/2021 Approved CHRIS CHRISTENSEN
Final 6/2/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/2/2021 Approved CHRIS CHRISTENSEN
Green Building Final 6/2/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 6/2/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 6/2/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 6/2/2021 Approved CHRIS CHRISTENSEN
Final 7/2/2021 Conditional Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/2/2021 SGSOV Approved CHRIS CHRISTENSEN
Final 7/8/2021 OK to Issue CofO CHRIS CHRISTENSEN