6225 E BEARD ST 90042
Certificate Information: 6225 E BEARD ST 90042
- Application / Permit
- 20014-20000-02637
- Plan Check / Job No.
- B20VN08455
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRREGULAR 20'-0" X 24'-0" FOR TWO NEW BEDROOMS, ONE NEW BATHROOM, LAUNDRY ROOM, AND TO EXTEND THE (E) DINING ROOM. ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 10/05/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO in Progress on 11/23/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/2/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 8/6/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 8/19/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/2/2020 | HAYATO TSUCHIYA |
| Issued | 9/10/2020 | APPLICANT |
| CofO in Progress | 11/23/2020 | DAVID LEE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/26/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 8/6/2020 | JENNIFER LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | A & R Reconstruction Inc; Lic. No.: 1015009-B | 8041 FELIX AVENUE BELL GARDENS, CA 90201 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Partial Approval | DAVID LEE |
| Footing/Foundation/Slab | 9/17/2020 | Partial Approval | DAVID LEE |
| Pre-Inspection | 9/17/2020 | Approved | DAVID LEE |
| BUILDING-Rough-Frame | 10/1/2020 | Partial Approval | DAVID LEE |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Partial Approval | DAVID LEE |
| ELECTRICAL-Rough | 10/13/2020 | Approved | DAVID LEE |
| HVAC-Rough | 10/13/2020 | Approved | DAVID LEE |
| Interior/Exterior Lathing | 10/13/2020 | Approved | DAVID LEE |
| PLUMBING-Rough | 10/13/2020 | Approved | DAVID LEE |
| BUILDING-Rough-Frame | 10/15/2020 | Approved | DAVID LEE |
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Approved | DAVID LEE |
| Footing/Foundation/Slab | 10/15/2020 | Approved | DAVID LEE |
| Green Building Rough | 10/15/2020 | Approved | DAVID LEE |
| Insulation | 10/16/2020 | Approved | DAVID LEE |
| Drywall Nailing | 10/21/2020 | Approved | DAVID LEE |
| ELECTRICAL-Final | 11/23/2020 | Approved | DAVID LEE |
| Final | 11/23/2020 | OK to Issue CofO | DAVID LEE |
| Gas Test | 11/23/2020 | Approved | DAVID LEE |
| Green Building Final | 11/23/2020 | Approved | DAVID LEE |
| HVAC-Final | 11/23/2020 | Approved | DAVID LEE |
| PLUMBING-Final | 11/23/2020 | Approved | DAVID LEE |
| SGSOV-Seismic Gas S/O Valve | 11/23/2020 | SGSOV Approved | DAVID LEE |
| Service/Power Release | 11/23/2020 | Approved | DAVID LEE |
| Smoke Detectors | 11/23/2020 | Approved | DAVID LEE |