11801 W ALBERS ST 91607
Certificate Information: 11801 W ALBERS ST 91607
- Application / Permit
- 20014-20000-02626
- Plan Check / Job No.
- B20VN08414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 24'-1" X 13'-11" AND 5'-9" X 17' TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Current Status
- CofO Issued on 3/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/2/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/2/2020 | APPLICANT |
| Plan Check Approved | 9/2/2020 | SELLA BENYAMIN |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 3/3/2022 | ARAM AVEDISIAN |
| Permit Finaled | 3/10/2022 | RONALD MYRICK |
| CofO Issued | 3/10/2022 | RONALD MYRICK |
| Permit Finaled | 3/10/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/9/2020 | ADRIAN CASTRO |
| Specific Plan | Cleared | 8/5/2020 | ERIN NASH |
| Construction near power lines | Cleared | 8/26/2020 | RIDWAN HARDY |
Contact Information
| Contractor | California Construction Center Inc; Lic. No.: 891847-B | 12509 OXNARD #209 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/21/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/13/2020 | Partial Approval | BRENDAN LOONEY |
| Special/Order Compliance | 10/13/2020 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/20/2020 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/26/2020 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 10/26/2020 | Partial Approval | THOMAS FINNILA |
| Pre-Inspection | 10/26/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 10/26/2020 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 11/5/2020 | Partial Inspection | THOMAS FINNILA |
| Sewer | 11/5/2020 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/8/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/8/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 2/8/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 2/16/2021 | Conditional Approval | DANIEL ORRANTE |
| Deputy Wood Construction | 2/17/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/19/2021 | Partial Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 2/19/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/19/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | DANIEL ORRANTE |
| ELECTRICAL-Rough | 3/18/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 3/18/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/18/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 3/18/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/8/2021 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 4/8/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/8/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 4/14/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/14/2021 | Partial Approval | JUSTIN HAWLEY |
| Pre-Inspection | 4/14/2021 | Partial Inspection | CALEB MEISTER |
| Pre-Inspection | 4/14/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Shower Pan | 4/14/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 4/22/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/22/2021 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/14/2021 | No Access for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/14/2021 | No Access for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/13/2022 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Final | 1/13/2022 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Final | 1/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 1/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 1/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/26/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/26/2022 | Approved | ARAM AVEDISIAN |
| Green Building Final | 1/26/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 1/26/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 1/26/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/3/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 2/3/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 2/3/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/14/2022 | Approved | THOMAS FINNILA |
| Final | 2/14/2022 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 2/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 2/14/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 3/3/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 3/3/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | ARAM AVEDISIAN |