5326 N DONNA AVE 91356
Certificate Information: 5326 N DONNA AVE 91356
- Application / Permit
- 20014-20000-02589
- Plan Check / Job No.
- B20VN08311
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL; REMOVE ENTIRE DWELLING (27'-9" LINEAR FEET OF WALL TO REMAIN ON NORTH SIDE; ADD 59'-9" X 98' SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/13/2020
- Issuing Office
- Current Status
- CofO Issued on 6/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/22/2020 | SELLA BENYAMIN |
| Quality Review Completed | 7/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/28/2020 | APPLICANT |
| Plan Check Approved | 11/13/2020 | SELLA BENYAMIN |
| Issued | 11/13/2020 | APPLICANT |
| CofO in Progress | 5/19/2022 | DAVID SANDOVAL |
| CofO Issued | 6/2/2022 | MICHAEL SMITH |
| Permit Finaled | 6/2/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 8/24/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/8/2020 | JOHN TRIANTAFYLLOS |
| Trees in Parkway | Cleared | 9/8/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/18/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 9/25/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 10/1/2020 | GUILLERMO PETRA |
| Disturb/Remove Protected Trees | Cleared | 10/31/2020 | SELLA BENYAMIN |
Contact Information
| Contractor | Lightning Construction & Design Inc; Lic. No.: 951122-B | 6047 TAMPA AVE #303 TARZANA, CA 91356 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2020 | Partial Approval | DAVID SANDOVAL |
| Underground Mechanical | 11/18/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/2/2020 | Approved | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 12/4/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/4/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 3/4/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 3/4/2021 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 3/5/2021 | Conditional Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/10/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 3/10/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/10/2021 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/19/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/19/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 2/1/2022 | Corrections Issued | DAVID SANDOVAL |
| Pool Piping | 2/7/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Underground Mechanical | 2/9/2022 | Approved | DAVID SANDOVAL |
| Final | 4/22/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 4/22/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 4/22/2022 | Approved | DAVID SANDOVAL |
| Final | 5/9/2022 | Partial Approval | DAVID SANDOVAL |
| Final | 5/19/2022 | OK to Issue CofO | DAVID SANDOVAL |