13016 W ADDISON ST 91423
Certificate Information: 13016 W ADDISON ST 91423
- Application / Permit
- 20014-20000-02583
- Plan Check / Job No.
- B20VN08298
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 24' X 19'-2" MASTER BEDROOM ADDITION AND (N) 12'-10" X 10'-1" RECROOM ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/25/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 7/6/2020 | APPLICANT |
| Plan Check Approved | 3/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/16/2021 | APPLICANT |
| CofO in Progress | 3/15/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 3/15/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/11/2022 | MICHAEL SMITH |
| CofO Issued | 4/11/2022 | MICHAEL SMITH |
| Permit Finaled | 4/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/17/2021 | MARKOS PEREZ-BRAN |
| Certificate of Compliance | Cleared | 3/1/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 3/1/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 3/10/2021 | MARTIN FRAGOSO |
Contact Information
| Contractor | Davis Development Group; Lic. No.: 575945-B | 4247 BLUEBELL AVE STUDIO CITY, CA 91604 |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2021 | Approved | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/30/2021 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 5/21/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 7/13/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/22/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/28/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/28/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/6/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/6/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 8/25/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/25/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/26/2021 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 8/26/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/31/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 11/2/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 11/2/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/8/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 11/8/2021 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | MATT KELLERMAN |
| Smoke Detectors | 11/8/2021 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/11/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 3/11/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/11/2022 | Approved | CHRISTOPHE COCHRAN |