8238 W GROVE ST 91040

Certificate Information: 8238 W GROVE ST 91040

Application / Permit
20014-20000-02579
Plan Check / Job No.
B20VN08290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 1' X 19' PORTION OF GARAGE AND CONVERT REMAINING 13' X 19' (E) DETACHED GARAGE AND ADD 26' X 20'-6" IRREGULAR SHAPED TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/8/2021
Issuing Office
Valley
Current Status
CofO Issued on 5/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 RAPHAEL ROSAS
Corrections Issued 6/28/2020 RAPHAEL ROSAS
Applicant returned to address corrections 9/18/2020 RAPHAEL ROSAS
Applicant returned to address corrections 11/10/2020 RAPHAEL ROSAS
Applicant returned to address corrections 12/4/2020 RAPHAEL ROSAS
Applicant returned to address corrections 1/25/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/22/2021 RAPHAEL ROSAS
Plan Check Approved 6/22/2021 RAPHAEL ROSAS
Building Plans Picked Up 6/23/2021 APPLICANT
Issued 7/8/2021 APPLICANT
CofO in Progress 5/19/2023 WILLIAM WREN
Permit Finaled 5/23/2023 MICHAEL SMITH
CofO Issued 5/23/2023 MICHAEL SMITH
Permit Finaled 5/23/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/7/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 7/23/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/29/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 9/30/2020 KIRK LINKLATER
Low Impact Development Cleared 6/14/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/14/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2021 Approved DAVID MATSON
Footing/Foundation/Slab 1/24/2022 Approved MATTHEW NELSON
Wood Frame 1/31/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 2/2/2022 No Access for Inspection MATTHEW NELSON
PLUMBING-Rough 2/4/2022 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 2/24/2022 Approved MATTHEW NELSON
HVAC-Rough 3/3/2022 Approved MATTHEW NELSON
PLUMBING-Rough 3/3/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/8/2022 Approved MATTHEW NELSON
Green Building Rough 3/8/2022 Approved MATTHEW NELSON
Insulation 3/11/2022 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 3/11/2022 Conditional Approval GREGG CUMMINGS
Underground Mechanical 3/11/2022 Partial Approval GREGG CUMMINGS
Insulation 3/16/2022 Approved MATTHEW NELSON
Drywall Nailing 3/21/2022 Approved MATTHEW NELSON
Underground Mechanical 3/25/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/4/2022 Approved MATTHEW NELSON
Gas Test 6/15/2022 Approved MATTHEW NELSON
Final 5/9/2023 Corrections Issued WILLIAM WREN
Green Building Final 5/9/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved WILLIAM WREN
Smoke Detectors 5/9/2023 Approved WILLIAM WREN
Final 5/16/2023 OK to Issue CofO WILLIAM WREN