1225-1227 W 41ST ST 90037
Certificate Information: 1225-1227 W 41ST ST 90037
- Application / Permit
- 20014-20000-02571
- Plan Check / Job No.
- B20VN08272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 47'6"X32'0" IRREGULAR SHAPED 2ND FLOOR ADU ADDITION & REMODEL TO (E) SFD. NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 5/12/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MARVEL DELACRUZ |
| Corrections Issued | 7/23/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 7/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/29/2020 | APPLICANT |
| Plan Check Approved | 3/11/2021 | MARVEL DELACRUZ |
| Issued | 5/12/2021 | APPLICANT |
| CofO in Progress | 1/17/2024 | SABAS ALONSO |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
| CofO Issued | 2/1/2024 | DEROLD HAUFF |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | THOMAS LANG |
| Sewer availability | Cleared | 8/6/2020 | THOMAS LANG |
| ZI | Cleared | 12/15/2020 | RAFAEL FONTES |
| Low Impact Development | Cleared | 1/21/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/22/2021 | CECILIO NAVARRO |
| Green Code | Cleared | 3/11/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Ahn'S Construction; Lic. No.: 1022756-B | 13330 BLOOMFIELD AVENUE SUITE 220 NORWALK, CA 90650 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 6/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Pre-Inspection | 6/24/2021 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/1/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 2/16/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 3/18/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 4/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 5/19/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 6/6/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 6/8/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/22/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/6/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 11/17/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/23/2022 | Corrections Issued | JULIAN AMAYA |
| HVAC-Rough | 11/23/2022 | Corrections Issued | JULIAN AMAYA |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | JULIAN AMAYA |
| Wood Frame | 11/23/2022 | Not Ready for Inspection | JULIAN AMAYA |
| ELECTRICAL-Rough | 12/15/2022 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 12/15/2022 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 12/15/2022 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/27/2022 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 12/27/2022 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/28/2022 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/28/2022 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 12/28/2022 | Not Ready for Inspection | BRENDAN MORELLI |
| Wood Frame | 2/17/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/27/2023 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 2/27/2023 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 5/3/2023 | No Access for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/15/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/15/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 7/21/2023 | No Access for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/21/2023 | No Access for Inspection | BRENDAN MORELLI |
| Final | 7/21/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 7/21/2023 | No Access for Inspection | BRENDAN MORELLI |
| HVAC-Final | 7/21/2023 | No Access for Inspection | BRENDAN MORELLI |
| PLUMBING-Final | 7/21/2023 | No Access for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 7/21/2023 | No Access for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 8/2/2023 | Approved | SABAS ALONSO |
| Final | 8/2/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/2/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 8/2/2023 | Approved | SABAS ALONSO |
| Final | 9/13/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/30/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | SABAS ALONSO |
| Final | 12/11/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Approved | SABAS ALONSO |
| Final | 12/19/2023 | Corrections Issued | SABAS ALONSO |
| Final | 1/16/2024 | OK to Issue CofO | SABAS ALONSO |