1225-1227 W 41ST ST 90037

Certificate Information: 1225-1227 W 41ST ST 90037

Application / Permit
20014-20000-02571
Plan Check / Job No.
B20VN08272
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
47'6"X32'0" IRREGULAR SHAPED 2ND FLOOR ADU ADDITION & REMODEL TO (E) SFD. NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 5/12/2021
Issuing Office
Metro
Current Status
CofO Issued on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 MARVEL DELACRUZ
Corrections Issued 7/23/2020 MARVEL DELACRUZ
Quality Review Completed 7/28/2020 STEVEN KIM
Building Plans Picked Up 7/29/2020 APPLICANT
Plan Check Approved 3/11/2021 MARVEL DELACRUZ
Issued 5/12/2021 APPLICANT
CofO in Progress 1/17/2024 SABAS ALONSO
Permit Finaled 2/1/2024 DEROLD HAUFF
CofO Issued 2/1/2024 DEROLD HAUFF
Permit Finaled 2/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/5/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/6/2020 THOMAS LANG
Sewer availability Cleared 8/6/2020 THOMAS LANG
ZI Cleared 12/15/2020 RAFAEL FONTES
Low Impact Development Cleared 1/21/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/22/2021 CECILIO NAVARRO
Green Code Cleared 3/11/2021 MARVEL DELACRUZ

Contact Information

Contractor Ahn'S Construction; Lic. No.: 1022756-B 13330 BLOOMFIELD AVENUE   SUITE 220    NORWALK, CA 90650
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/24/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/24/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 6/24/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Pre-Inspection 6/24/2021 Partial Inspection JESUS PINEDA
BUILDING-Rough-Frame 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Final 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/30/2021 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 8/2/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/1/2021 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 2/16/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 3/18/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/29/2022 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 4/12/2022 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 5/19/2022 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 6/6/2022 Partial Inspection JOAQUIN GREENOUGH
Special/Order Compliance 6/8/2022 Partial Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/22/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/6/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 11/17/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 11/23/2022 Corrections Issued JULIAN AMAYA
HVAC-Rough 11/23/2022 Corrections Issued JULIAN AMAYA
PLUMBING-Rough 11/23/2022 Corrections Issued JULIAN AMAYA
Wood Frame 11/23/2022 Not Ready for Inspection JULIAN AMAYA
ELECTRICAL-Rough 12/15/2022 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 12/15/2022 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 12/15/2022 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 12/27/2022 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 12/27/2022 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 12/28/2022 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 12/28/2022 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 12/28/2022 Not Ready for Inspection BRENDAN MORELLI
Wood Frame 2/17/2023 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 2/27/2023 Partial Approval STUART CHAPMAN
Wood Frame 2/27/2023 Partial Approval STUART CHAPMAN
Wood Frame 5/3/2023 No Access for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 5/15/2023 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/15/2023 Approved STUART CHAPMAN
Green Building Rough 5/15/2023 Approved STUART CHAPMAN
Drywall Nailing 7/21/2023 No Access for Inspection BRENDAN MORELLI
ELECTRICAL-Final 7/21/2023 No Access for Inspection BRENDAN MORELLI
Final 7/21/2023 Corrections Issued BRENDAN MORELLI
Green Building Final 7/21/2023 No Access for Inspection BRENDAN MORELLI
HVAC-Final 7/21/2023 No Access for Inspection BRENDAN MORELLI
PLUMBING-Final 7/21/2023 No Access for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 7/21/2023 No Access for Inspection BRENDAN MORELLI
Drywall Nailing 8/2/2023 Approved SABAS ALONSO
Final 8/2/2023 Corrections Issued SABAS ALONSO
Green Building Final 8/2/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 8/2/2023 Approved SABAS ALONSO
Final 9/13/2023 Not Ready for Inspection SABAS ALONSO
Final 11/30/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Not Ready SABAS ALONSO
Final 12/11/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Approved SABAS ALONSO
Final 12/19/2023 Corrections Issued SABAS ALONSO
Final 1/16/2024 OK to Issue CofO SABAS ALONSO