6506 N MARY ELLEN AVE 91401
Certificate Information: 6506 N MARY ELLEN AVE 91401
- Application / Permit
- 20014-20000-02569
- Plan Check / Job No.
- B20VN08258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING PATIO TO LIVING AREA; ADD 31' X 19'-9" AND 25'-11" X 6'-6" TO EXISTING SINGLE FAMILY DWELLING; ADD 14'-7" X 47'-2" PATIO COVER TO REAR OF DWELLING
- Permit Issued
- Issued on 10/6/2020
- Issuing Office
- Current Status
- CofO Issued on 3/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2020 | SELLA BENYAMIN |
| Corrections Issued | 6/25/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/1/2020 | APPLICANT |
| Plan Check Approved | 9/25/2020 | SELLA BENYAMIN |
| Issued | 10/6/2020 | APPLICANT |
| CofO in Progress | 4/26/2021 | RICHARD DOCKUS |
| Permit Finaled | 3/12/2022 | MICHAEL SMITH |
| CofO Issued | 3/12/2022 | MICHAEL SMITH |
| Permit Finaled | 3/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 7/1/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 9/15/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/25/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/14/2020 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 10/27/2020 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/13/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/2/2020 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/2/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/2/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 12/2/2020 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 12/2/2020 | Approved | BRENDAN LOONEY |
| Insulation | 12/15/2020 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/15/2020 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/24/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/24/2020 | Approved | BRENDAN LOONEY |
| Insulation | 12/24/2020 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/30/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 12/30/2020 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/31/2020 | Approved | BRENDAN LOONEY |
| Shower Pan | 12/31/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/13/2021 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/22/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 4/13/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 4/13/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/13/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 4/23/2021 | OK to Issue CofO | RICHARD DOCKUS |
| Smoke Detectors | 4/23/2021 | Approved | RICHARD DOCKUS |