8241 N ST CLAIR AVE 91605

Certificate Information: 8241 N ST CLAIR AVE 91605

Application / Permit
20014-20000-02524
Plan Check / Job No.
B20VN08140
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 4'-2" X 26'-6" TO EXTEND AND REMODEL (E) BEDROOMS/BATHROOMS PER WFPP.
Permit Issued
Issued on 9/22/2020
Issuing Office
Current Status
CofO Issued on 8/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/22/2020 JENNIFER LEE
Corrections Issued 7/23/2020 JENNIFER LEE
Applicant returned to address corrections 9/4/2020 LUIS RINCON
Plan Check Approved 9/21/2020 JENNIFER LEE
Issued 9/22/2020 APPLICANT
CofO in Progress 7/23/2021 DANIEL DREW
Permit Finaled 8/19/2022 DANIEL ORRANTE
CofO Issued 8/19/2022 DANIEL ORRANTE
Permit Finaled 8/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 7/24/2020 JASON SHEETS
Eng Process Fee Ord 176,300 Cleared 8/13/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 8/13/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/8/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 10/15/2020 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/21/2020 Approved JOHN HAYES
Wood Frame 11/6/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/12/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/12/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/17/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 12/16/2020 Partial Approval JOHN HAYES
Wood Frame 1/19/2021 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 1/26/2021 Approved JOHN HAYES
Green Building Rough 1/26/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 1/26/2021 Approved JOHN HAYES
Drywall Nailing 2/8/2021 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 2/8/2021 Partial Approval JOHN HAYES
Shower Pan 2/8/2021 Approved JOHN HAYES
Interior/Exterior Lathing 3/3/2021 Approved JOHN HAYES
Drywall Nailing 7/23/2021 Approved DANIEL DREW
ELECTRICAL-Final 7/23/2021 Approved DANIEL DREW
Final 7/23/2021 OK to Issue CofO DANIEL DREW
Footing/Foundation/Slab 7/23/2021 Approved DANIEL DREW
Green Building Final 7/23/2021 Approved DANIEL DREW
HVAC-Final 7/23/2021 Approved DANIEL DREW
PLUMBING-Final 7/23/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 7/23/2021 Approved DANIEL DREW