7446 N LINDLEY AVE 91335

Certificate Information: 7446 N LINDLEY AVE 91335

Application / Permit
20014-20000-02521
Plan Check / Job No.
B20VN08133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 7' 6" X 11' 10" TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/22/2020 GURUNATH NESARAJAH
Corrections Issued 6/22/2020 GURUNATH NESARAJAH
Building Plans Picked Up 6/26/2020 APPLICANT
Plan Check Approved 8/13/2020 JEROME MAGAT PALMA
Issued 3/18/2021 APPLICANT
CofO in Progress 6/6/2025 ARUTYUN MADATYAN
CofO Issued 7/21/2025 DANIEL ORRANTE
Permit Finaled 7/21/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/28/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/28/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/29/2020 ADRIAN CASTRO
Sewer availability Cleared 7/29/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/31/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/13/2021 Approved VINCENT HANLEY
Green Building Rough 6/18/2021 Not Ready for Inspection VINCENT HANLEY
Sewer 6/18/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval VINCENT HANLEY
Green Building Rough 1/21/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 1/21/2022 Approved VINCENT HANLEY
PLUMBING-Rough 1/21/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/8/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/8/2022 Approved VINCENT HANLEY
Green Building Rough 4/8/2022 Approved VINCENT HANLEY
Insulation 4/8/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/8/2022 Approved VINCENT HANLEY
Drywall Nailing 5/26/2023 Approved JEFFREY BULL
Shower Pan 5/26/2023 Approved JEFFREY BULL
Final 4/25/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 4/25/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 4/25/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 6/5/2025 Approved ARUTYUN MADATYAN
Final 6/5/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 6/5/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 6/5/2025 Approved ARUTYUN MADATYAN