17735 W HORACE ST 91344
Certificate Information: 17735 W HORACE ST 91344
- Application / Permit
- 20014-20000-02517
- Plan Check / Job No.
- B20VN08123
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 12'-4" X 36'-2" ATTACHED GARAGE AND ADD NEW 18'-11" X 26'-4" 2-CAR GARAGE PER ENGINEERING
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofO Issued on 4/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | JENNIFER LEE |
| Corrections Issued | 7/11/2020 | JENNIFER LEE |
| Plan Check Approved | 10/13/2020 | JENNIFER LEE |
| Issued | 10/20/2020 | APPLICANT |
| CofO in Progress | 4/15/2021 | DAVID SCANTLIN |
| Permit Finaled | 4/26/2021 | JOHN JANSON |
| CofO Issued | 4/26/2021 | JOHN JANSON |
| Permit Finaled | 4/26/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Prime Builders Construction Co; Lic. No.: 953200-B | 10349 DENSMORE AVENUE GRANADA HILLS, CA 91344 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 2/25/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/6/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/14/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 4/14/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 4/14/2021 | Approved | DAVID SCANTLIN |
| Final | 4/14/2021 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 4/14/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 4/14/2021 | Approved | DAVID SCANTLIN |
| HVAC-Final | 4/14/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 4/14/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2021 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 4/14/2021 | Approved | DAVID SCANTLIN |