4480 N SHERMAN OAKS AVE 91403
Certificate Information: 4480 N SHERMAN OAKS AVE 91403
- Application / Permit
- 20014-20000-02509
- Plan Check / Job No.
- B20VN08104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO (E) ONE STORY SFD, MAINTAIN (E) ATTACHED TWO CAR GARAGE AND PROPOSE TWO STORY SFD ADDITION _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | DAWN MC NULTY |
| Corrections Issued | 7/17/2020 | DAWN MC NULTY |
| Quality Review Completed | 7/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Plan Check Approved | 3/17/2021 | DAWN MC NULTY |
| No Progress | 3/22/2021 | DAWN MC NULTY |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 2/27/2024 | VINCENT HANLEY |
| Permit Finaled | 8/15/2025 | JOHN JANSON |
| CofO Issued | 8/15/2025 | JOHN JANSON |
| Permit Finaled | 8/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| CPC | Cleared | 7/31/2020 | LAUREN PADICK |
| Low Impact Development | Cleared | 2/25/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/3/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/3/2021 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 3/17/2021 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 3/17/2021 | DAWN MC NULTY |
Contact Information
| Architect | , ; Lic. No.: C37632 | 3786 LA CRESCENTA AVE. #201 GLENDALE, CA 91208 |
| Contractor | Owner-Builder | , |
| Engineer | Yogurtian,, Arpinee; Lic. No.: C49916 | 2529 FOOTHILL BLVD, STE 208 LA CRESCENTA, CA 91214 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2021 | Partial Inspection | RONALD COWAN |
| Sewer | 5/26/2021 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 8/12/2021 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 9/13/2021 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 9/21/2021 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 9/21/2021 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 9/24/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 3/15/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 3/29/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 5/9/2022 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/23/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 5/25/2022 | Approved | DAVID SANDOVAL |
| Gas Test | 6/2/2022 | Approved | PETER FOLLING |
| Insulation | 2/9/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 2/9/2023 | Partial Approval | JESUS PINEDA |
| Shower Pan | 2/9/2023 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/13/2023 | Approved | VINCENT HANLEY |
| Insulation | 2/13/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | VINCENT HANLEY |
| MERV13>=Rough | 2/13/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 2/13/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/14/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/22/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/12/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 11/15/2023 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 2/21/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/21/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 2/21/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/22/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/22/2024 | Approved | VINCENT HANLEY |
| Final | 2/27/2024 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 2/27/2024 | Approved | VINCENT HANLEY |
| MERV13>=Final | 2/27/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Approved | VINCENT HANLEY |