7033-7035 N ATOLL AVE 91605

Certificate Information: 7033-7035 N ATOLL AVE 91605

Application / Permit
20014-20000-02507
Plan Check / Job No.
B20VN08091
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19' X 19'-4" ADDITION FOR NEW BEDROOM, BATHROOM, AND CLOSET. CONVERT 22'-7" X 11'-8" PORTION OF PATIO COVER AND 43'-1" X 33'-5" PORTION OF (E) DWELLING TO ACCESSORY DWELLING UNIT (1502 SF) PER LAMC 12.22 A.33(c) and (e) . CONVERT 14'-7" X 11'-8" PORTION OF PATIO COVER TO ENLARGE SFD LIVING ROOM.
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2020 APPLICANT
Assigned to Plan Check Engineer 6/22/2020 JEROME MAGAT PALMA
Corrections Issued 6/22/2020 JEROME MAGAT PALMA
Plan Check Approved 8/2/2021 JEROME MAGAT PALMA
Building Plans Picked Up 8/4/2021 APPLICANT
Issued 8/12/2021 APPLICANT
CofO in Progress 2/8/2024 JOSE AVILA
Permit Finaled 3/6/2024 RUBEN SALAS
CofO Issued 3/6/2024 RUBEN SALAS
Permit Finaled 3/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/29/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/29/2021 GABRIEL ROBLES
Sewer availability Cleared 7/6/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/9/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Paibul,, Seni; Lic. No.: C24061 31960 VIA DEL SENOR      HOMELAND, CA 92548

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 11/9/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/11/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/21/2022 No Access for Inspection CHRISTOPHE COCHRAN
Green Building Rough 4/21/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/20/2022 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 6/3/2022 Partial Approval CHRISTOPHE COCHRAN
Pre-Inspection 7/5/2022 Partial Approval RAFAEL CORTES
Pre-Inspection 8/31/2022 Approved RAFAEL CORTES
BUILDING-Rough-Frame 12/12/2022 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 12/12/2022 Approved JOHN COLEMAN
Rough-Elec/Plmb/HVAC 12/12/2022 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 12/16/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 12/27/2022 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 12/27/2022 Approved KIRK SANDERS
PLUMBING-Rough 12/27/2022 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Approved KIRK SANDERS
Insulation 2/3/2023 Approved KIRK SANDERS
Drywall Nailing 2/13/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/10/2023 Corrections Issued KIRK SANDERS
Final 7/10/2023 Corrections Issued KIRK SANDERS
Gas Test 7/10/2023 Approved KIRK SANDERS
HVAC-Final 7/10/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 7/10/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 7/26/2023 Not Ready for Inspection KIRK SANDERS
Final 7/26/2023 Corrections Issued KIRK SANDERS
Green Building Final 7/26/2023 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 7/26/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 12/4/2023 Approved KIRK SANDERS
ELECTRICAL-Final 12/4/2023 Approved KIRK SANDERS
Final 12/4/2023 Corrections Issued KIRK SANDERS
Final 1/26/2024 Corrections Issued JOSE AVILA
Green Building Final 1/26/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Not Ready JOSE AVILA
Smoke Detectors 1/26/2024 Approved JOSE AVILA
Final 1/31/2024 Corrections Issued JOSE AVILA
Final 2/7/2024 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved JOSE AVILA