16422-16424 W INDEX ST 91344

Certificate Information: 16422-16424 W INDEX ST 91344

Application / Permit
20014-20000-02493
Plan Check / Job No.
B20VN08065
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6' x 11' AND 18' x 3'9" ADDITION AND CONVERT THE (E) 19'10" X 18' GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 7/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 JEFFREY TANGONAN
Corrections Issued 6/19/2020 JEFFREY TANGONAN
Applicant returned to address corrections 7/14/2020 JEFFREY TANGONAN
Issued 7/24/2020 APPLICANT
CofO in Progress 3/10/2021 MARK JOHNSON
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/25/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/25/2020 LEE GUILBEAUX
Grading Pre-Inspection Cleared 7/6/2020 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 7/7/2020 LEE GUILBEAUX
Sewer availability Cleared 7/7/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/7/2020 LEE GUILBEAUX
Public Works-Sewers Cleared 7/7/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/27/2020 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 8/7/2020 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/18/2020 Partial Approval MARK JOHNSON
Green Building Rough 9/18/2020 Not Ready for Inspection MARK JOHNSON
MERV13>=Rough 9/18/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 9/30/2020 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 9/30/2020 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 9/30/2020 Approved MARK JOHNSON
HVAC-Rough 9/30/2020 Partial Approval MARK JOHNSON
MERV13>=Rough 9/30/2020 Approved MARK JOHNSON
PLUMBING-Rough 9/30/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 10/13/2020 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 10/13/2020 Approved MARK JOHNSON
Green Building Rough 10/13/2020 Approved MARK JOHNSON
HVAC-Rough 10/13/2020 Approved MARK JOHNSON
PLUMBING-Rough 10/13/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 10/19/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/20/2020 Approved MARK JOHNSON
Insulation 11/24/2020 Approved MARK JOHNSON
Drywall Nailing 11/25/2020 Approved MARK JOHNSON
Shower Pan 12/8/2020 Approved MARK JOHNSON
Final 2/25/2021 Corrections Issued MARK JOHNSON
Green Building Final 2/25/2021 Approved MARK JOHNSON
MERV13>=Final 2/25/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Not Ready MARK JOHNSON
Smoke Detectors 2/25/2021 Approved MARK JOHNSON
ELECTRICAL-Final 3/2/2021 Approved MARK JOHNSON
HVAC-Final 3/2/2021 Approved MARK JOHNSON
PLUMBING-Final 3/2/2021 Approved MARK JOHNSON
Final 3/9/2021 OK to Issue CofO MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved MARK JOHNSON