2412 W NORWALK AVE 90041
Certificate Information: 2412 W NORWALK AVE 90041
- Application / Permit
- 20014-20000-02492
- Plan Check / Job No.
- B20VN08056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADD 5'-6" X 30'-4" TO FIRST FLOOR AND SECOND FLOOR AND 9'-4" X 12'-10" ADDITION TO SECOND FLOOR ONLY OF (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 4/23/2021
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/17/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/21/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/24/2020 | APPLICANT |
| Plan Check Approved | 1/28/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/23/2021 | APPLICANT |
| CofO in Progress | 4/19/2022 | CRAIG VAUGHAN |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/4/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2020 | ELAINE LEI |
| Sewer availability | Cleared | 9/17/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 10/30/2020 | MATTHEW CRAIG |
| Tract Map conditions | Cleared | 11/9/2020 | MIGUEL GAMBOA |
| Tract Map conditions | Cleared | 11/9/2020 | MIGUEL GAMBOA |
| GPI Written Notices | Cleared | 1/26/2021 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 1/26/2021 | SEWADA ZADOORAN MILAGARDI |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | ELAINE LEI |
Contact Information
| Contractor | Vaneli Construction Inc; Lic. No.: 933782-B | 4022 VITRINA LANE PALMDALE, CA 93551 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/18/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/24/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 6/29/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 8/2/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/25/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/25/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 8/25/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 8/25/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/25/2021 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 8/25/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 8/26/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/26/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 9/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 9/13/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/13/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 9/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/15/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 9/15/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/20/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 9/20/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 9/23/2021 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 9/23/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 9/27/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 9/30/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 10/7/2021 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 12/1/2021 | Approved | JUSTIN HAWLEY |
| Sewer | 12/6/2021 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 4/4/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/4/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 4/12/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/18/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/18/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 4/18/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/18/2022 | Approved | CRAIG VAUGHAN |