7762 N FERNCOLA AVE 91352
Certificate Information: 7762 N FERNCOLA AVE 91352
- Application / Permit
- 20014-20000-02481
- Plan Check / Job No.
- B20VN08019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE AND ADDITION OF 2 STORY TO (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2020 | PINANK PATEL |
| Corrections Issued | 6/17/2020 | PINANK PATEL |
| Plan Check Approved | 7/27/2020 | PINANK PATEL |
| Issued | 8/11/2020 | APPLICANT |
| CofO in Progress | 11/19/2021 | WILLIAM KUEHN |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/28/2020 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 6/29/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/29/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/30/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arsen, Adzhemyan; Lic. No.: C89103 | 1010 RALEIGH ST 107 LA, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2020 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 8/17/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 8/17/2020 | Partial Approval | BEAU COLLINS |
| Wood Frame | 8/28/2020 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 9/21/2020 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/21/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 9/21/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/21/2020 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/24/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 9/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/30/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 9/30/2020 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 9/30/2020 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 9/30/2020 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 10/22/2020 | Not Ready for Inspection | BEAU COLLINS |
| ELECTRICAL-Rough | 11/13/2020 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 11/13/2020 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/24/2020 | Partial Approval | BEAU COLLINS |
| Underground Mechanical | 2/25/2021 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 3/17/2021 | Partial Approval | BEAU COLLINS |
| ELECTRICAL-Rough | 3/17/2021 | Partial Approval | BEAU COLLINS |
| PLUMBING-Rough | 3/17/2021 | Partial Approval | BEAU COLLINS |
| Gas Test | 4/12/2021 | Partial Approval | BEAU COLLINS |
| Interior/Exterior Lathing | 4/12/2021 | Approved | BEAU COLLINS |
| Special/Order Compliance | 4/27/2021 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 11/1/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 11/1/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 11/1/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 11/1/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | WILLIAM KUEHN |
| Final | 11/18/2021 | OK to Issue CofO | WILLIAM KUEHN |
| Green Building Final | 11/18/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 11/18/2021 | Approved | WILLIAM KUEHN |