9745-9747 N DANUBE AVE 91343
Certificate Information: 9745-9747 N DANUBE AVE 91343
- Application / Permit
- 20014-20000-02472
- Plan Check / Job No.
- B20VN07994
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 3'-4" X 19'-6" TO ATTACHED GARAGE AND CONVERT TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- CofO Issued on 6/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | SELLA BENYAMIN |
| Corrections Issued | 6/26/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/2/2020 | APPLICANT |
| Issued | 2/23/2021 | APPLICANT |
| CofO in Progress | 5/27/2022 | RAUL OLAGI |
| Permit Finaled | 6/1/2022 | MICHAEL SMITH |
| CofO Issued | 6/1/2022 | MICHAEL SMITH |
| Permit Finaled | 6/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 7/10/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 11/10/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/22/2021 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 10/22/2021 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 10/22/2021 | Corrections Issued | RAUL OLAGI |
| MERV13>=Rough | 10/22/2021 | Not Ready for Inspection | RAUL OLAGI |
| Underground Mechanical | 10/22/2021 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 10/27/2021 | Not Ready for Inspection | ALAN MORELOS |
| PLUMBING-Rough | 10/27/2021 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 11/2/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 11/2/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 11/2/2021 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 11/2/2021 | Approved | RAUL OLAGI |
| Sewer | 11/2/2021 | Not Ready for Inspection | RAUL OLAGI |
| Insulation | 11/10/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/10/2021 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 11/18/2021 | Approved | RAUL OLAGI |
| Sewer | 11/18/2021 | Approved | RAUL OLAGI |
| Shower Pan | 11/24/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | RAUL OLAGI |
| Final | 5/27/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 5/27/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/27/2022 | Approved | RAUL OLAGI |
| MERV13>=Final | 5/27/2022 | Approved | RAUL OLAGI |
| MERV13>=Rough | 5/27/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/27/2022 | Approved | RAUL OLAGI |