5148 N OTIS AVE 91356
Certificate Information: 5148 N OTIS AVE 91356
- Application / Permit
- 20014-20000-02461
- Plan Check / Job No.
- B20VN07933
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- ADD 7'-5" X 20'-6" TO (E) GARAGE TO ATTACH (E) GARAGE TO (E) ALQ AND CONVERT 23'-11" X 20'-6" PORTION TO ACCESSORY LIVING QUARTER ALL WORK PER WFPP NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT (FIRE DEP) COMPLY WITH DEPARTMENT ORDER PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/22/2021
- Issuing Office
- Current Status
- CofO Issued on 3/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/10/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/10/2020 | APPLICANT |
| Applicant returned to address corrections | 1/26/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 2/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 2/22/2021 | APPLICANT |
| CofO in Progress | 3/8/2022 | DAVID SANDOVAL |
| No Progress | 3/11/2022 | ROBERT GOLD |
| CofO in Progress | 3/18/2022 | ROBERT GOLD |
| Permit Finaled | 3/22/2022 | JOHN JANSON |
| CofO Issued | 3/22/2022 | JOHN JANSON |
| Permit Finaled | 3/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 8/26/2020 | MARC WOERSCHING |
| Tract Map conditions | Cleared | 8/26/2020 | MARC WOERSCHING |
| Tract Map conditions | Cleared | 8/26/2020 | MARC WOERSCHING |
| Low Impact Development | Cleared | 10/19/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/29/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/4/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 2/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 2/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Miscellaneous | Cleared | 2/22/2021 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2021 | Partial Approval | DAVID SANDOVAL |
| Wood Frame | 5/28/2021 | Partial Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 6/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 6/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 6/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| Sewer | 6/29/2021 | No Access for Inspection | DAVID SANDOVAL |
| Insulation | 7/30/2021 | Not Ready for Inspection | PETER FOLLING |
| Insulation | 8/26/2021 | No Access for Inspection | DAVID SANDOVAL |
| Insulation | 8/30/2021 | Partial Inspection | RYAN SALAZAR |
| Drywall Nailing | 9/1/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 9/1/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 9/2/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 9/13/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 9/13/2021 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 9/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Underground Mechanical | 9/15/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Underground Mechanical | 9/21/2021 | Partial Approval | DAVID SANDOVAL |
| Underground Mechanical | 9/23/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Masonry Wall/Backfill | 10/21/2021 | No Access for Inspection | DAVID SANDOVAL |
| Pre-Inspection | 12/14/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 1/20/2022 | Order to Comply Issued | DAVID SANDOVAL |
| HVAC-Final | 1/20/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Final | 1/20/2022 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 2/7/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 2/7/2022 | Approved | DAVID SANDOVAL |
| Final | 2/7/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 2/7/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 2/7/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 2/7/2022 | Approved | DAVID SANDOVAL |
| Final | 3/8/2022 | OK to Issue CofO | DAVID SANDOVAL |