14238 W CALIFA ST 91401

Certificate Information: 14238 W CALIFA ST 91401

Application / Permit
20014-20000-02440
Plan Check / Job No.
B20VN07882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TOO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
Permit Issued
Issued on 7/31/2020
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/12/2020 MOHAMMAD ESMAILI
Corrections Issued 6/12/2020 MOHAMMAD ESMAILI
Building Plans Picked Up 6/18/2020 APPLICANT
Issued 7/31/2020 APPLICANT
CofO in Progress 12/5/2020 MICHEL ABAJAN
CofO Issued 3/5/2022 MICHAEL SMITH
Permit Finaled 3/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/18/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 6/18/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/30/2020 GUILLERMO PETRA
Sewer availability Cleared 7/30/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2020 No Access for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 8/4/2020 Approved WILLIAM KUEHN
PLUMBING-Rough 8/4/2020 Partial Inspection WILLIAM KUEHN
ELECTRICAL-Rough 8/31/2020 Not Ready for Inspection WILLIAM KUEHN
PLUMBING-Rough 8/31/2020 Not Ready for Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 8/31/2020 Corrections Issued WILLIAM KUEHN
Insulation 9/2/2020 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 9/14/2020 Approved WILLIAM KUEHN
Drywall Nailing 9/14/2020 Approved WILLIAM KUEHN
Green Building Rough 9/14/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 9/14/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 9/14/2020 Approved WILLIAM KUEHN
Shower Pan 9/14/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 9/22/2020 Partial Inspection WILLIAM KUEHN
Sewer 10/5/2020 Approved WILLIAM KUEHN
Underground Mechanical 10/5/2020 Partial Inspection WILLIAM KUEHN
Final 10/23/2020 Corrections Issued MATTHEW NELSON
Green Building Final 10/23/2020 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 10/23/2020 Corrections Issued MATTHEW NELSON
Final 11/4/2020 Corrections Issued WILLIAM KUEHN
Green Building Final 11/4/2020 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Not Ready WILLIAM KUEHN
Smoke Detectors 11/4/2020 Not Ready for Inspection WILLIAM KUEHN
Final 11/17/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 11/17/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 11/17/2020 Partial Inspection MICHEL ABAJAN
Final 12/4/2020 OK to Issue CofO MICHEL ABAJAN
Green Building Final 12/4/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/4/2020 Approved MICHEL ABAJAN