6837 N WILLIS AVE 91405
Certificate Information: 6837 N WILLIS AVE 91405
- Application / Permit
- 20014-20000-02438
- Plan Check / Job No.
- B20VN07867
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 12'-6" X 23'-3" TO EXTEND (E) LIVING/DINING ROOM, REMODEL (E) KITCHEN, CONVERT PORTION OF (E) KITCHEN TO (N) LAUNDRY ROOM, REMOVE INTERIOR GARAGE DOOR, REMODEL (E) BATHROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/15/2020
- Issuing Office
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | JENNIFER LEE |
| Corrections Issued | 6/29/2020 | JENNIFER LEE |
| Plan Check Approved | 7/20/2020 | RAPHAEL ROSAS |
| No Progress | 8/23/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 9/3/2020 | RAPHAEL ROSAS |
| Issued | 9/15/2020 | APPLICANT |
| CofO in Progress | 4/27/2021 | JENNIFER RABUCHIN |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 7/6/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Precision Construction Experts Inc; Lic. No.: 1026997-B | 16656 CALLE ARBOLADA PACIFIC PALISADES, CA 90272 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 9/28/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/6/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 10/6/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Insulation | 10/6/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/26/2020 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/26/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 10/26/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 10/26/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/29/2020 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 10/29/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/30/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 10/30/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/2/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/2/2020 | Approved | WILLIAM KUEHN |
| Insulation | 11/2/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/2/2020 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 11/2/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 11/6/2020 | No Access for Inspection | WILLIAM KUEHN |
| Gas Test | 11/6/2020 | No Access for Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/6/2020 | No Access for Inspection | WILLIAM KUEHN |
| Insulation | 11/6/2020 | No Access for Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/6/2020 | No Access for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Drywall Nailing | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Gas Test | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 2/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 2/2/2021 | Corrections Issued | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/8/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/8/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/8/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 2/8/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/8/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 2/8/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/22/2021 | No Access for Inspection | MICHAEL TEMPLE |
| Final | 3/22/2021 | No Access for Inspection | MICHAEL TEMPLE |
| HVAC-Final | 3/22/2021 | No Access for Inspection | MICHAEL TEMPLE |
| PLUMBING-Final | 3/22/2021 | No Access for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Final | 3/26/2021 | No Access for Inspection | MICHAEL TEMPLE |
| Final | 3/26/2021 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Final | 3/26/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 3/26/2021 | No Access for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Final | 4/8/2021 | Approved | JENNIFER RABUCHIN |
| Final | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/8/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/26/2021 | Approved | JENNIFER RABUCHIN |
| Final | 4/26/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/26/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/26/2021 | Approved | JENNIFER RABUCHIN |