6837 N WILLIS AVE 91405

Certificate Information: 6837 N WILLIS AVE 91405

Application / Permit
20014-20000-02438
Plan Check / Job No.
B20VN07867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 12'-6" X 23'-3" TO EXTEND (E) LIVING/DINING ROOM, REMODEL (E) KITCHEN, CONVERT PORTION OF (E) KITCHEN TO (N) LAUNDRY ROOM, REMOVE INTERIOR GARAGE DOOR, REMODEL (E) BATHROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
CofO Issued on 6/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 JENNIFER LEE
Corrections Issued 6/29/2020 JENNIFER LEE
Plan Check Approved 7/20/2020 RAPHAEL ROSAS
No Progress 8/23/2020 RAPHAEL ROSAS
Plan Check Approved 9/3/2020 RAPHAEL ROSAS
Issued 9/15/2020 APPLICANT
CofO in Progress 4/27/2021 JENNIFER RABUCHIN
CofO Issued 6/5/2021 MICHAEL SMITH
Permit Finaled 6/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/6/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/6/2020 GABRIEL ROBLES

Contact Information

Contractor Precision Construction Experts Inc; Lic. No.: 1026997-B 16656 CALLE ARBOLADA      PACIFIC PALISADES, CA 90272
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/28/2020 Approved WILLIAM KUEHN
Footing/Foundation/Slab 9/28/2020 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 10/6/2020 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Partial Inspection WILLIAM KUEHN
Green Building Rough 10/6/2020 Not Ready for Inspection WILLIAM KUEHN
Insulation 10/6/2020 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 10/26/2020 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 10/26/2020 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 10/26/2020 Not Ready for Inspection MATTHEW NELSON
Wood Frame 10/26/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/29/2020 Not Ready for Inspection JOHN HAYES
Wood Frame 10/29/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/30/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 10/30/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/30/2020 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 10/30/2020 Corrections Issued JENNIFER RABUCHIN
Wood Frame 10/30/2020 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/2/2020 Not Ready for Inspection WILLIAM KUEHN
Green Building Rough 11/2/2020 Approved WILLIAM KUEHN
Insulation 11/2/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 11/2/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 11/2/2020 Approved WILLIAM KUEHN
Drywall Nailing 11/6/2020 No Access for Inspection WILLIAM KUEHN
Gas Test 11/6/2020 No Access for Inspection WILLIAM KUEHN
Green Building Rough 11/6/2020 No Access for Inspection WILLIAM KUEHN
Insulation 11/6/2020 No Access for Inspection WILLIAM KUEHN
Interior/Exterior Lathing 11/6/2020 No Access for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Drywall Nailing 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Gas Test 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
HVAC-Final 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Final 2/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 2/2/2021 Corrections Issued ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/8/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 2/8/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/8/2021 Corrections Issued JENNIFER RABUCHIN
Final 2/8/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 2/8/2021 Approved JENNIFER RABUCHIN
Green Building Final 2/8/2021 Approved JENNIFER RABUCHIN
Green Building Rough 2/8/2021 Approved JENNIFER RABUCHIN
HVAC-Final 2/8/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Final 2/8/2021 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 2/8/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/22/2021 No Access for Inspection MICHAEL TEMPLE
Final 3/22/2021 No Access for Inspection MICHAEL TEMPLE
HVAC-Final 3/22/2021 No Access for Inspection MICHAEL TEMPLE
PLUMBING-Final 3/22/2021 No Access for Inspection MICHAEL TEMPLE
ELECTRICAL-Final 3/26/2021 No Access for Inspection MICHAEL TEMPLE
Final 3/26/2021 Corrections Issued MICHAEL TEMPLE
HVAC-Final 3/26/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Final 3/26/2021 No Access for Inspection MICHAEL TEMPLE
ELECTRICAL-Final 4/8/2021 Approved JENNIFER RABUCHIN
Final 4/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/8/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/8/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 4/8/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/26/2021 Approved JENNIFER RABUCHIN
Final 4/26/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/26/2021 Approved JENNIFER RABUCHIN
HVAC-Final 4/26/2021 Approved JENNIFER RABUCHIN