6524 W OLYMPIC PL 90035
Certificate Information: 6524 W OLYMPIC PL 90035
- Application / Permit
- 20014-20000-02430
- Plan Check / Job No.
- B20VN07836
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 24' X 13'-5" ADDITION TO (E) SFD FOR NEW BEDROOM, FULL BATHROOM AND STORAGE. REMODEL TO CREATE NEW STUDY ROOM AND CLOSET. WORK PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- CofO Issued on 3/31/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2020 | ROSENDO MEDINA |
| Corrections Issued | 6/16/2020 | ROSENDO MEDINA |
| Issued | 8/25/2020 | APPLICANT |
| CofO in Progress | 3/19/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/31/2021 | DEROLD HAUFF |
| CofO Issued | 3/31/2021 | DEROLD HAUFF |
| Permit Finaled | 3/31/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/25/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 6/25/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | RENZ SORIANO |
| ZI | Cleared | 8/13/2020 | JONATHAN KAPLAN |
| HPOZ | Cleared | 8/17/2020 | JONATHAN KAPLAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/14/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/24/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 11/5/2020 | Approved | DAVID CHAN |
| METHANE-Barrier | 11/5/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 11/5/2020 | Approved | DAVID CHAN |
| Wood Frame | 11/5/2020 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 11/13/2020 | Not Ready for Inspection | DAVID CHAN |
| Insulation | 11/13/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/13/2020 | Not Ready for Inspection | DAVID CHAN |
| Drywall Nailing | 11/23/2020 | Conditional Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 12/7/2020 | Partial Approval | DAVID CHAN |
| Green Building Rough | 12/7/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 12/7/2020 | Approved | DAVID CHAN |
| METHANE-Rough | 12/7/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 3/18/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/18/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 3/18/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/18/2021 | Approved | CHRIS CHRISTENSEN |