24754 S BOMBAY AVE 90744

Certificate Information: 24754 S BOMBAY AVE 90744

Application / Permit
20014-20000-02427
Plan Check / Job No.
B20VN07822
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (23' X 24') IRREGULAR SHAPED MASTER BEDROOM, BEDROOM# 3 WITH CLOSET ADDITION TO (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/1/2020
Issuing Office
Current Status
CofO Issued on 1/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2020 APPLICANT
Assigned to Plan Check Engineer 6/17/2020 RAPHAEL ROSAS
Corrections Issued 6/19/2020 RAPHAEL ROSAS
Applicant returned to address corrections 7/27/2020 THOMAS SHERMAN
Plan Check Approved 8/17/2020 TROY DEGUZMAN
Issued 10/1/2020 APPLICANT
CofO in Progress 1/5/2026 EUGENE CASSIDY
Permit Finaled 1/7/2026 ANSON MAGLASANG
CofO Issued 1/7/2026 ANSON MAGLASANG
Permit Finaled 1/7/2026 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/30/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/30/2020 GABRIEL ROBLES
Sewer availability Cleared 7/30/2020 GABRIEL ROBLES

Contact Information

Contractor Unity Construction; Lic. No.: 1017730-B 12512 CHANDLER BLVD #216      VALLEY VILLAGE, CA 91607
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2020 Approved JOHN KLARIN
METHANE-Barrier 10/8/2020 Approved JOHN KLARIN
METHANE-Subgrade 10/8/2020 Approved JOHN KLARIN
Wood Frame 10/19/2020 Partial Inspection JOHN KLARIN
Insulation 10/22/2020 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Approval JOHN KLARIN
PLUMBING-Rough 11/16/2020 Corrections Issued JOHN KLARIN
Shower Pan 12/2/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 12/8/2020 Partial Approval EUGENE CASSIDY
Drywall Nailing 12/14/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 12/18/2020 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 12/23/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/27/2021 Approved JOHN KLARIN
Final 1/27/2021 Corrections Issued JOHN KLARIN
Green Building Final 1/27/2021 Corrections Issued JOHN KLARIN
Green Building Rough 1/27/2021 Approved JOHN KLARIN
METHANE-Final 1/27/2021 Approved JOHN KLARIN
METHANE-Rough 1/27/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 1/27/2021 Approved JOHN KLARIN
ELECTRICAL-Final 1/5/2026 Approved EUGENE CASSIDY
Final 1/5/2026 OK to Issue CofO EUGENE CASSIDY
Green Building Final 1/5/2026 Approved EUGENE CASSIDY
HVAC-Final 1/5/2026 Approved EUGENE CASSIDY
PLUMBING-Final 1/5/2026 Approved EUGENE CASSIDY