8364 N OUTLAND VIEW DR 91352

Certificate Information: 8364 N OUTLAND VIEW DR 91352

Application / Permit
20014-20000-02418
Plan Check / Job No.
B20VN07791
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT; EXISTING STORAGE TO REMAIN
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
Issued on 1/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/12/2020 SELLA BENYAMIN
Corrections Issued 6/15/2020 SELLA BENYAMIN
Building Plans Picked Up 6/16/2020 APPLICANT
Plan Check Approved 7/29/2020 SELLA BENYAMIN
Issued 1/26/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/19/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 6/19/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 6/19/2020 GUILLERMO PETRA
Sewer availability Cleared 6/19/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 7/13/2020 MATTHEW CRAIG

Contact Information

Contractor Advanced General Construction; Lic. No.: 951083-B 6545 HAZELTINE AVE # 212      VAN NUYS, CA 91401

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/4/2021 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 2/10/2021 Partial Approval BEAU COLLINS
Deputy Drilled-In Anchors 2/16/2021 Conditional Approval BEAU COLLINS
PLUMBING-Rough 2/18/2021 No Access for Inspection BEAU COLLINS
PLUMBING-Rough 2/26/2021 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 3/10/2021 Corrections Issued BEAU COLLINS
ELECTRICAL-Rough 3/10/2021 Corrections Issued BEAU COLLINS
Green Building Rough 3/10/2021 Not Ready for Inspection BEAU COLLINS
MERV13>=Rough 3/10/2021 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 3/25/2021 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 3/25/2021 Partial Approval BEAU COLLINS
Green Building Rough 3/25/2021 Not Ready for Inspection BEAU COLLINS
MERV13>=Rough 3/25/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 4/12/2021 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 4/12/2021 Approved BEAU COLLINS
Green Building Rough 4/12/2021 Approved BEAU COLLINS
Interior/Exterior Lathing 4/12/2021 Partial Inspection BEAU COLLINS
Shower Pan 4/12/2021 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 5/24/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 5/24/2021 Not Ready for Inspection JOHN HAYES
Final 5/24/2021 Corrections Issued JOHN HAYES
Green Building Final 5/24/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 5/24/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 5/24/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 5/24/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 5/24/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/1/2021 Approved GABRIEL HERRERA
ELECTRICAL-Final 6/1/2021 Approved GABRIEL HERRERA
Final 6/1/2021 Conditional Approval GABRIEL HERRERA
Green Building Final 6/1/2021 Approved GABRIEL HERRERA
HVAC-Final 6/1/2021 Approved GABRIEL HERRERA
MERV13>=Final 6/1/2021 Approved GABRIEL HERRERA
PLUMBING-Final 6/1/2021 Approved GABRIEL HERRERA
SGSOV-Seismic Gas S/O Valve 6/1/2021 SGSOV Approved GABRIEL HERRERA
Smoke Detectors 6/1/2021 Approved GABRIEL HERRERA