Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 4/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 NILOOFAR MEHRAIN
Corrections Issued 6/16/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 6/25/2020 APPLICANT
Issued 12/1/2020 APPLICANT
CofO in Progress 4/1/2022 ROBERT GOLD
Permit Finaled 4/11/2022 MICHAEL SMITH
CofO Issued 4/11/2022 MICHAEL SMITH
Permit Finaled 4/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 10/23/2020 YVAINNE GALSIM
Sewer availability Cleared 10/30/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/4/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/12/2020 ADRIAN CASTRO

Contact Information

Contractor Benson Restoration And Construction Inc; Lic. No.: 543921-B 9027 CANOGA AVENUE UNIT D      CANOGA PARK, CA 91301

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
MORRIS JACKSON, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2021 Approved STEVEN BACK
Footing/Foundation/Slab 2/5/2021 Approved STEVEN BACK
PLUMBING-Rough 2/8/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 3/2/2021 Partial Approval STEVEN BACK
Wood Frame 3/2/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 7/2/2021 Conditional Approval STEVEN BACK
ELECTRICAL-Rough 7/27/2021 Approved DAVID SANDOVAL
HVAC-Rough 7/27/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 7/27/2021 Approved DAVID SANDOVAL
Wood Frame 7/27/2021 Partial Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Corrections Issued STEVEN BACK
HVAC-Rough 9/24/2021 Approved STEVEN BACK
Deputy Wood Construction 9/27/2021 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 10/6/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Approved STEVEN BACK
Green Building Rough 10/6/2021 Approved STEVEN BACK
Interior/Exterior Lathing 10/6/2021 Partial Approval STEVEN BACK
Insulation 10/15/2021 Approved SHAVONNE ESPINOZA
Drywall Nailing 11/2/2021 Approved JAVIER RAMOS JR
Shower Pan 11/2/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/10/2021 Approved MORRIS JACKSON
Gas Test 2/18/2022 Approved SEAN HAUPT
ELECTRICAL-Final 3/8/2022 Corrections Issued SEAN HAUPT
Final 3/8/2022 Corrections Issued SEAN HAUPT
Green Building Final 3/8/2022 Approved SEAN HAUPT
HVAC-Final 3/8/2022 Approved SEAN HAUPT
PLUMBING-Final 3/8/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Not Ready SEAN HAUPT
Service/Power Release 3/8/2022 Approved SEAN HAUPT
Smoke Detectors 3/8/2022 Corrections Issued SEAN HAUPT
ELECTRICAL-Final 3/14/2022 Approved ROBERT GOLD
Final 3/14/2022 OK to Issue CofO ROBERT GOLD
PLUMBING-Final 3/14/2022 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Approved ROBERT GOLD
Smoke Detectors 3/14/2022 Approved ROBERT GOLD