12248 W STAGG ST 91605
Certificate Information: 12248 W STAGG ST 91605
- Application / Permit
- 20014-20000-02385
- Plan Check / Job No.
- B20VN07729
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21' X 41' 7" ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 6/14/2021
- Issuing Office
- Current Status
- CofO Issued on 8/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 6/17/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/12/2021 | GURUNATH NESARAJAH |
| Issued | 6/14/2021 | APPLICANT |
| Building Plans Picked Up | 6/23/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 8/19/2022 | DANIEL ORRANTE |
| CofO Issued | 8/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/6/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/6/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/16/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/12/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 10/12/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 10/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/28/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/28/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 11/3/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/22/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 12/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/22/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 12/22/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Piling/Pier/Caisson | 1/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 1/14/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 1/19/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 1/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 1/21/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/21/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/27/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 1/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 7/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 7/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 7/6/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 7/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 7/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 7/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 7/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 7/21/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Green Building Final | 7/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 7/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 7/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |