15142 W WEDDINGTON ST 91411
Certificate Information: 15142 W WEDDINGTON ST 91411
- Application / Permit
- 20014-20000-02382
- Plan Check / Job No.
- B20VN07719
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove portion of SFD. 2'-9" x 8'-11" addition, 4'-11 x 7'-10" addition, 36'-8" x 45'-6" irreg shaped addition and major remodel to (E) one story SFD.
- Permit Issued
- Issued on 4/11/2023
- Issuing Office
- Current Status
- Issued on 4/11/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/6/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 7/9/2020 | STEVEN KIM |
| Applicant returned to address corrections | 8/6/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/10/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| No Progress | 10/12/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/8/2023 | JEROME MAGAT PALMA |
| Issued | 4/11/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 10/7/2020 | ABDULLAH SADOZAI |
| ZI | Cleared | 10/15/2020 | RICHARD REASER |
| Low Impact Development | Cleared | 5/13/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/9/2022 | CARLOS AGUILERA |
| ZI | Cleared | 12/13/2022 | DANG NGUYEN |
| Roof/Waste drainage to street | Cleared | 1/18/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Harvey Ralph Donell; Lic. No.: 652651-B | 11715 SOUTH WILTON PLACE HAWTHORNE, CA 90250 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/5/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/15/2023 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/26/2023 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 6/27/2023 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/4/2023 | Partial Inspection | DAVID MATSON |
| Green Building Rough | 8/4/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 8/4/2023 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 8/9/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 8/9/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/30/2023 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 8/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/6/2023 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | THOMAS FINNILA |
| Deputy Wood Construction | 9/27/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/28/2023 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 12/18/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 12/18/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/19/2023 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 12/19/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 12/19/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 1/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 1/16/2024 | Corrections Issued | THOMAS FINNILA |
| Special/Order Compliance | 1/16/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/16/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 2/16/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 2/16/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/28/2024 | Approved | THOMAS FINNILA |
| HVAC-Rough | 2/28/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/28/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 3/1/2024 | Approved | THOMAS FINNILA |
| Wood Frame | 3/1/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/18/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 3/18/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/18/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 4/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 4/29/2024 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/12/2024 | Approved | JACK KARGODORIAN |
| Insulation | 6/12/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 6/24/2024 | Approved | RUBEN SALAS |
| ELECTRICAL-Rough | 11/19/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 11/19/2024 | Approved | JACK KARGODORIAN |
| Final | 2/19/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/19/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 2/19/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 2/19/2025 | Approved | JACK KARGODORIAN |
| Final | 6/5/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/5/2025 | Approved | JACK KARGODORIAN |
| Final | 6/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |