3274 S WOODBINE ST 90064

Certificate Information: 3274 S WOODBINE ST 90064

Application / Permit
20014-20000-02379
Plan Check / Job No.
B20VN07711
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE 313SF BEDROOM ADDITION AND REMODEL BATHROOM AT SECOND FLOOR AND ADD EXTERIOR DOOR AT FIRST FLOOR REAR BEDROOM.
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
Issued on 4/27/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 DAWN MC NULTY
Corrections Issued 7/7/2020 DAWN MC NULTY
Quality Review Completed 7/8/2020 CHON CHIO KUO
Building Plans Picked Up 7/10/2020 APPLICANT
Plan Check Approved 8/22/2020 DAWN MC NULTY
Issued 4/27/2022 APPLICANT

Permit Application Clearance Information

ZI Cleared 7/20/2020 LAUREN PADICK
Grading Pre-Inspection Cleared 7/23/2020 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 7/28/2020 DINAH GARIN
Sewer availability Cleared 7/28/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 8/21/2020 HISASHI KOBAYAKAWA

Contact Information

Contractor Nittay Inc; Lic. No.: 1033506-B 17941 VENTURA BLVD #204      ENCINO, CA 91316
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2023 Corrections Issued DAVID FEILER
Deputy Drilled-In Anchors 3/3/2023 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 3/4/2023 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 3/4/2023 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 3/25/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 4/26/2023 Approved CLAYTON GRAHAM
HVAC-Rough 4/26/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 4/26/2023 Approved CLAYTON GRAHAM
Deputy Wood Construction 4/27/2023 Conditional Approval CLAYTON GRAHAM
HVAC-Rough 5/1/2023 Approved CLAYTON GRAHAM
Insulation 5/1/2023 Partial Approval CLAYTON GRAHAM
Shower Pan 5/1/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 5/2/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Approved CLAYTON GRAHAM
Deputy Wood Construction 5/3/2023 Conditional Approval MICHAEL PELHAM
Insulation 5/5/2023 Not Ready for Inspection CLAYTON GRAHAM
Interior/Exterior Lathing 5/5/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 5/5/2023 Conditional Approval CLAYTON GRAHAM
Insulation 5/8/2023 Approved MICHAEL PELHAM
Interior/Exterior Lathing 5/8/2023 Partial Approval MICHAEL PELHAM
Interior/Exterior Lathing 5/9/2023 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 5/11/2023 Conditional Approval CLAYTON GRAHAM
Drywall Nailing 5/11/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 5/11/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 5/11/2023 Approved CLAYTON GRAHAM
MERV13>=Rough 5/11/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 8/11/2023 Approved CLAYTON GRAHAM
Drywall Nailing 8/11/2023 Approved CLAYTON GRAHAM
Final 8/11/2023 Corrections Issued CLAYTON GRAHAM
Footing/Foundation/Slab 8/11/2023 Approved CLAYTON GRAHAM
Green Building Final 8/11/2023 Not Ready for Inspection CLAYTON GRAHAM
MERV13>=Final 8/11/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Approved CLAYTON GRAHAM
Smoke Detectors 8/11/2023 Approved CLAYTON GRAHAM
Final 8/25/2023 Corrections Issued CLAYTON GRAHAM
Green Building Final 8/25/2023 Not Ready for Inspection CLAYTON GRAHAM