8417 N WHEATLAND AVE 91352

Certificate Information: 8417 N WHEATLAND AVE 91352

Application / Permit
20014-20000-02364
Plan Check / Job No.
B20VN07633
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
25'-3" X 46'-7" IRREG SHAPED ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE
Permit Issued
Issued on 11/17/2020
Issuing Office
Current Status
CofO Issued on 10/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 JEROME MAGAT PALMA
Corrections Issued 6/28/2020 JEROME MAGAT PALMA
Building Plans Picked Up 7/1/2020 APPLICANT
Plan Check Approved 11/17/2020 JEROME MAGAT PALMA
Issued 11/17/2020 APPLICANT
CofO in Progress 7/29/2021 WILLIAM KUEHN
Permit Finaled 10/5/2021 MICHAEL SMITH
CofO Issued 10/5/2021 MICHAEL SMITH
Permit Finaled 10/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 8/19/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/24/2020 ADRIAN CASTRO
Address approval Cleared 9/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/16/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/16/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 11/17/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/25/2020 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 12/1/2020 Partial Inspection BEAU COLLINS
Footing/Foundation/Slab 12/7/2020 Not Ready for Inspection JOHN HAYES
Sewer 12/15/2020 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 12/30/2020 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Partial Approval BEAU COLLINS
PLUMBING-Rough 1/20/2021 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 2/12/2021 Partial Approval BEAU COLLINS
HVAC-Rough 2/12/2021 Approved BEAU COLLINS
PLUMBING-Rough 2/12/2021 Partial Approval BEAU COLLINS
Wood Frame 2/12/2021 Partial Approval BEAU COLLINS
Insulation 2/26/2021 Approved BEAU COLLINS
Interior/Exterior Lathing 2/26/2021 Partial Approval BEAU COLLINS
Shower Pan 2/26/2021 Approved BEAU COLLINS
Drywall Nailing 3/8/2021 Approved BEAU COLLINS
Gas Test 3/8/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 7/21/2021 Approved THOMAS FINNILA
Final 7/21/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Final 7/21/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 7/21/2021 Approved THOMAS FINNILA
MERV13>=Final 7/21/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 7/21/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 7/21/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 7/28/2021 Approved WILLIAM KUEHN
Final 7/28/2021 OK to Issue CofO WILLIAM KUEHN
Green Building Final 7/28/2021 Approved WILLIAM KUEHN
HVAC-Final 7/28/2021 Approved WILLIAM KUEHN
MERV13>=Final 7/28/2021 Approved WILLIAM KUEHN
PLUMBING-Final 7/28/2021 Approved WILLIAM KUEHN