4106 N TOLAND WAY 90065
Certificate Information: 4106 N TOLAND WAY 90065
- Application / Permit
- 20014-20000-02350
- Plan Check / Job No.
- B20VN07596
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 11'-0" X 19'-0" (N) RECREATION ROOM ADDITION WITH A (N) BREEZEWAY UNDERNEATH TO REAR OF (E) SFD (ADDITION SHALL INCREASE (E) BUILDING HEIGHT)
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | MARVEL DELACRUZ |
| Corrections Issued | 7/9/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 7/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/13/2020 | APPLICANT |
| Applicant returned to address corrections | 8/19/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/15/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/29/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/16/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 3/26/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/20/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/17/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/7/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/13/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/20/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/15/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 1/10/2023 | MARVEL DELACRUZ |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 9/16/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
| CofO Issued | 9/18/2025 | DEROLD HAUFF |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/27/2020 | NASHYA JENSEN |
| ZI | Cleared | 8/27/2020 | NASHYA JENSEN |
| Roof/Waste drainage to street | Cleared | 8/31/2020 | CELINA MORENO |
| Sewer availability | Cleared | 8/31/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 2/26/2021 | MARVEL DELACRUZ |
| Green Code | Cleared | 5/13/2022 | MARVEL DELACRUZ |
Contact Information
| Architect | Lacson,, Renato S; Lic. No.: C12064 | 14026 ROSCOE BLVD PANORAMA CITY, CA 91402 |
| Contractor | Owner-Builder | , |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 21414 ARCOS DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/31/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/21/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/21/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 6/21/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 8/21/2023 | Partial Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 9/1/2023 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/1/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/11/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/21/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 9/22/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/22/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/22/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 10/2/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/11/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/30/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 12/8/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 3/14/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 3/14/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 3/14/2024 | Corrections Issued | BRIAN SULLIVAN |
| Structural Steel Frame | 3/14/2024 | Approved | BRIAN SULLIVAN |
| Final | 3/27/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 9/16/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |