15145 W MARTHA ST 91411
Certificate Information: 15145 W MARTHA ST 91411
- Application / Permit
- 20014-20000-02346
- Plan Check / Job No.
- B20VN07583
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPE ADDITION ( 16'-9" X 35' ) TO (E) SFD TO ENLARGE AND REMODEL (E) KITCHEN AND DINING ROOM, ADD NEW POWDER ROOM AND REMODEL (E) BATHROOM.
- Permit Issued
- Issued on 7/8/2020
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | LUIS RINCON |
| Corrections Issued | 6/11/2020 | LUIS RINCON |
| Applicant returned to address corrections | 6/25/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/7/2020 | ROSENDO MEDINA |
| Issued | 7/8/2020 | APPLICANT |
| CofO in Progress | 12/1/2020 | MICHEL ABAJAN |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/16/2020 | ADRIAN CASTRO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/18/2020 | Approved | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2020 | Approved | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/9/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 9/9/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/9/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| HVAC-Rough | 9/9/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 9/9/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2020 | Partial Inspection | WILLIAM KUEHN |
| Gas Test | 9/14/2020 | Partial Approval | WILLIAM KUEHN |
| Insulation | 9/18/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/18/2020 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 9/22/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/22/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/22/2020 | Approved | WILLIAM KUEHN |
| Shower Pan | 9/22/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 12/1/2020 | Approved | MICHEL ABAJAN |
| Final | 12/1/2020 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 12/1/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/1/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/1/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/1/2020 | Approved | MICHEL ABAJAN |