6903 N MATILIJA AVE 91405

Certificate Information: 6903 N MATILIJA AVE 91405

Application / Permit
20014-20000-02344
Plan Check / Job No.
B20VN07575
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 24'-8" X 28'-10" TO AND CONVERT EXISTING STORAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 4/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2020 APPLICANT
Assigned to Plan Check Engineer 7/27/2020 SELLA BENYAMIN
Corrections Issued 7/29/2020 SELLA BENYAMIN
Building Plans Picked Up 8/7/2020 APPLICANT
Plan Check Approved 1/22/2021 SELLA BENYAMIN
Issued 2/10/2021 APPLICANT
CofO in Progress 4/1/2022 RICHARD DOCKUS
Permit Finaled 4/5/2022 RONALD MYRICK
CofO Issued 4/5/2022 RONALD MYRICK
Permit Finaled 4/5/2022 RONALD MYRICK

Permit Application Clearance Information

Construction near power lines Cleared 12/10/2020 RIDWAN HARDY
Low Impact Development Cleared 12/10/2020 ANDRES COVARRUBIAS
Hydrant and Access approval Cleared 12/15/2020 MATTHEW CRAIG
Address approval Cleared 12/24/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/28/2020 ADRIAN CASTRO
Sewer availability Cleared 12/28/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/30/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 6/30/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 7/6/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 7/30/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 7/30/2021 Approved CHRISTOPHE COCHRAN
Sewer 7/30/2021 Approved CHRISTOPHE COCHRAN
Underground Mechanical 7/30/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/26/2021 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 8/26/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Approved RICHARD DOCKUS
Green Building Rough 8/26/2021 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 8/26/2021 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 9/8/2021 Partial Approval AMY COLIN
BUILDING-Rough-Frame 9/15/2021 Partial Approval AMY COLIN
HVAC-Rough 9/15/2021 Approved AMY COLIN
Insulation 10/8/2021 Approved RONALD COWAN
Drywall Nailing 10/20/2021 Corrections Issued ALAN MORELOS
Drywall Nailing 10/25/2021 Approved ALAN MORELOS
Special/Order Compliance 10/25/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/4/2021 Approved RICHARD DOCKUS
ELECTRICAL-Final 12/17/2021 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 2/7/2022 Approved RICHARD DOCKUS
Final 2/7/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 2/7/2022 Approved RICHARD DOCKUS
Green Building Rough 2/7/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 2/7/2022 Corrections Issued RICHARD DOCKUS
Final 3/2/2022 OK to Issue CofO RICHARD DOCKUS
Smoke Detectors 3/2/2022 Approved RICHARD DOCKUS