17273 W WESTBURY DR 91344

Certificate Information: 17273 W WESTBURY DR 91344

Application / Permit
20014-20000-02335
Plan Check / Job No.
B20VN07540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) SFD , GARAGE TO REMAIN. IRR. SHAPE (63'-9"X60'-5") FULLEY SPRINKLERED NFPA-13D
Permit Issued
Issued on 9/24/2021
Issuing Office
Valley
Current Status
Issued on 9/24/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 MOHAMMAD ESMAILI
Corrections Issued 7/2/2020 MOHAMMAD ESMAILI
Quality Review Completed 7/14/2020 OMID HEDAYAT
Building Plans Picked Up 7/16/2020 APPLICANT
Plan Check Approved 9/13/2021 MOHAMMAD ESMAILI
Issued 9/24/2021 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 4/8/2021 ORVAL HERNANDEZ-MARCI
BHO/Hillside ordinance Cleared 4/16/2021 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 4/16/2021 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 4/16/2021 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 4/16/2021 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 4/16/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/16/2021 GUILLERMO PETRA
Sewer availability Cleared 4/16/2021 GUILLERMO PETRA
Miscellaneous Cleared 4/21/2021 DANG NGUYEN
Roof/Waste drainage to street Cleared 4/22/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 5/7/2021 KIRK LINKLATER
Distance to fire station Cleared 6/8/2021 KURT CORRAL
GPI Written Notices Cleared 9/8/2021 OMID HEDAYAT

Contact Information

Contractor Owner-Builder       ,
Engineer 1010, Raleigh St; Lic. No.: C89103    APT 107    GLENDALE, CA

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/11/2022 No Access for Inspection SEAN HAUPT
PLUMBING-Rough 1/14/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 2/11/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Corrections Issued STEVEN BACK
Rough-Elec/Plmb/HVAC 3/14/2023 Approved STEVEN BACK
Special/Order Compliance 3/14/2023 Corrections Issued STEVEN BACK
Deputy Wood Construction 3/22/2023 Approved JEFFREY PARD
Deputy Wood Construction 4/5/2023 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Approved SEAN WIRCH
Green Building Rough 6/6/2023 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 6/6/2023 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 11/7/2023 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 11/7/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/7/2023 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 11/7/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 11/8/2023 No Access for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 11/15/2023 Approved DAVID SCANTLIN
Insulation 10/28/2025 Approved STEVEN BACK
Drywall Nailing 5/22/2026 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Final 5/22/2026 Corrections Issued CHRISTOPHER WILSON
Shower Pan 5/22/2026 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 6/1/2026 Approved STEVEN BACK
Shower Pan 6/1/2026 Approved STEVEN BACK