608 N LILLIAN WAY 90004

Certificate Information: 608 N LILLIAN WAY 90004

Application / Permit
20014-20000-02323
Plan Check / Job No.
B20VN07508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-1" X 19' IRREGULAR SHAPED ADDITION FOR NEW FAMILY ROOM & 8' X 4' ADDITION TO FOR NEW SHOWER TO (E) SINGLE FAMILY DWELLING AND REPLACE DRIVEWAY GATE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
CofO Issued on 1/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/19/2020 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/24/2020 APPLICANT
Applicant returned to address corrections 8/7/2020 ROSENDO MEDINA
Applicant returned to address corrections 9/8/2020 ALFRED RAMIREZ
Issued 9/15/2020 APPLICANT
CofO in Progress 1/11/2021 CHRIS CHRISTENSEN
Permit Finaled 1/21/2021 DEROLD HAUFF
CofO Issued 1/21/2021 DEROLD HAUFF
Permit Finaled 1/21/2021 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/13/2020 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 8/13/2020 ELAINE LEI
Sewer availability Cleared 8/13/2020 ELAINE LEI
ZI Cleared 8/13/2020 SUKI GERSHENHORN
Eng Process Fee Ord 176,300 Cleared 8/14/2020 ELAINE LEI
Low Impact Development Cleared 8/27/2020 SARAH YOUSSEF

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 9/17/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 9/17/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/28/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/7/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/7/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 10/7/2020 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/7/2020 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 10/7/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/7/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/9/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/9/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 10/9/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 10/9/2020 Approved CHRIS CHRISTENSEN
Shower Pan 10/9/2020 Approved CHRIS CHRISTENSEN
Wood Frame 10/9/2020 Approved CHRIS CHRISTENSEN
Insulation 10/14/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/14/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/21/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 12/15/2020 Approved CHRIS CHRISTENSEN
Final 12/15/2020 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 12/15/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 12/15/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 12/15/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 12/15/2020 Approved CHRIS CHRISTENSEN
Final 12/31/2020 Corrections Issued CHRIS CHRISTENSEN
Final 1/11/2021 OK to Issue CofO CHRIS CHRISTENSEN