5629 N NATICK AVE 91411

Certificate Information: 5629 N NATICK AVE 91411

Application / Permit
20014-20000-02322
Plan Check / Job No.
B20VN07503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
PROPOSED ADDITION ( 14'-6" X 12'-7" ) FOR NEW MASTER BEDROOM, REMODEL (E) BEDROOM FOR NEW MASTER BATHROOM AND CLOSET, AND NEW 23'-3" X 13'-7" ATTACHED COVERED PATIO ADDITION. ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 1/20/2021
Issuing Office
Current Status
Issued on 1/20/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/5/2020 ROSENDO MEDINA
Corrections Issued 6/8/2020 ROSENDO MEDINA
Plan Check Approved 1/5/2021 SARKIS HARABEDIAN
Issued 1/20/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/25/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 12/1/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/10/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Munroe,, Massie; Lic. No.: C59905 PO BOX 189      LA CANADA FLINTRIDGE, CA 91012

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2021 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 2/19/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/1/2021 Partial Approval JENNIFER RABUCHIN
Insulation 3/1/2021 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/12/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 5/12/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 5/12/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 5/12/2021 Approved MARK JOHNSON
PLUMBING-Rough 5/12/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 5/18/2021 Approved JENNIFER RABUCHIN
Green Building Rough 5/18/2021 Approved JENNIFER RABUCHIN
Insulation 5/18/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 5/18/2021 Partial Approval JENNIFER RABUCHIN
Shower Pan 5/18/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 5/24/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/24/2021 Approved MORRIS JACKSON
Final 7/1/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 7/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/1/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 7/1/2021 Approved ARTHUR SARGSYAN