13923-13925 W WEIDNER ST 91331

Certificate Information: 13923-13925 W WEIDNER ST 91331

Application / Permit
20014-20000-02317
Plan Check / Job No.
B20VN07484
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADD 5' X 8' LAUNDRY ROOM TO (E) DUPLEX WITH EXTERIOR ACCESS ONLY. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/9/2020
Issuing Office
Current Status
CofO Issued on 1/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 ROSENDO MEDINA
Corrections Issued 6/4/2020 ROSENDO MEDINA
Applicant returned to address corrections 6/19/2020 GURUNATH NESARAJAH
Plan Check Approved 7/2/2020 RAPHAEL ROSAS
Issued 7/9/2020 APPLICANT
Building Plans Picked Up 7/14/2020 APPLICANT
CofO in Progress 11/9/2020 MICHEL ABAJAN
CofO Issued 1/11/2021 MICHAEL SMITH
Permit Finaled 1/11/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/24/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/24/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/14/2020 Approved MICHEL ABAJAN
METHANE-Barrier 8/14/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 8/14/2020 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 9/17/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/21/2020 Approved MICHEL ABAJAN
Gas Test 9/21/2020 Approved MICHEL ABAJAN
Green Building Rough 9/21/2020 Approved MICHEL ABAJAN
METHANE-Rough 9/21/2020 Approved MICHEL ABAJAN
Insulation 9/24/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/24/2020 Approved MICHEL ABAJAN
Drywall Nailing 9/29/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/15/2020 Approved MICHEL ABAJAN
Final 10/15/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 10/15/2020 Approved MICHEL ABAJAN
PLUMBING-Final 10/15/2020 Approved MICHEL ABAJAN
Smoke Detectors 10/15/2020 Approved MICHEL ABAJAN
Final 10/28/2020 Not Ready for Inspection MICHEL ABAJAN
Final 11/9/2020 OK to Issue CofO MICHEL ABAJAN