13730 W COMMUNITY ST 91402
Certificate Information: 13730 W COMMUNITY ST 91402
- Application / Permit
- 20014-20000-02316
- Plan Check / Job No.
- B20VN07480
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 15' X 19' AND 14' X 15' FOR NEW BEDROOMS/BATHROOMS, REMODEL THROUGHOUT (E) 1-STORY SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | TROY DEGUZMAN |
| Corrections Issued | 6/9/2020 | TROY DEGUZMAN |
| Building Plans Picked Up | 6/9/2020 | APPLICANT |
| Applicant returned to address corrections | 8/20/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 9/15/2020 | JENNIFER LEE |
| Plan Check Approved | 10/1/2020 | JENNIFER LEE |
| Issued | 10/6/2020 | APPLICANT |
| CofO in Progress | 2/1/2022 | GREGG CUMMINGS |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
| CofO Issued | 2/17/2022 | MICHAEL SMITH |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 10/6/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/9/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/23/2020 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 2/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/11/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/11/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 3/11/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 3/11/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 3/11/2021 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 3/22/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 3/22/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/30/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 3/30/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 3/30/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/30/2021 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 3/30/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/14/2021 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 4/14/2021 | Partial Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/28/2021 | Partial Approval | GREGG CUMMINGS |
| Final | 9/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Final | 9/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 9/17/2021 | No Access for Inspection | GREGG CUMMINGS |
| Final | 1/20/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/20/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/20/2022 | Approved | GREGG CUMMINGS |
| Final | 1/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 1/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/1/2022 | Approved | GREGG CUMMINGS |
| Final | 2/1/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/1/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/1/2022 | Approved | GREGG CUMMINGS |