13730 W COMMUNITY ST 91402

Certificate Information: 13730 W COMMUNITY ST 91402

Application / Permit
20014-20000-02316
Plan Check / Job No.
B20VN07480
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 15' X 19' AND 14' X 15' FOR NEW BEDROOMS/BATHROOMS, REMODEL THROUGHOUT (E) 1-STORY SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 10/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 TROY DEGUZMAN
Corrections Issued 6/9/2020 TROY DEGUZMAN
Building Plans Picked Up 6/9/2020 APPLICANT
Applicant returned to address corrections 8/20/2020 JENNIFER LEE
Applicant returned to address corrections 9/15/2020 JENNIFER LEE
Plan Check Approved 10/1/2020 JENNIFER LEE
Issued 10/6/2020 APPLICANT
CofO in Progress 2/1/2022 GREGG CUMMINGS
Permit Finaled 2/17/2022 MICHAEL SMITH
CofO Issued 2/17/2022 MICHAEL SMITH
Permit Finaled 2/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/9/2020 GUILLERMO PETRA
Sewer availability Cleared 9/9/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 10/6/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/9/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 10/23/2020 Partial Approval GREGG CUMMINGS
Drywall Nailing 2/23/2021 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Approved GREGG CUMMINGS
Green Building Rough 2/23/2021 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 3/11/2021 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 3/11/2021 Approved GREGG CUMMINGS
Green Building Rough 3/11/2021 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 3/11/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 3/11/2021 Corrections Issued GREGG CUMMINGS
Insulation 3/22/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 3/22/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 3/30/2021 Approved GREGG CUMMINGS
Drywall Nailing 3/30/2021 Approved GREGG CUMMINGS
Green Building Rough 3/30/2021 Approved GREGG CUMMINGS
HVAC-Rough 3/30/2021 Partial Approval GREGG CUMMINGS
Shower Pan 3/30/2021 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/14/2021 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 4/14/2021 Partial Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 4/28/2021 Partial Approval GREGG CUMMINGS
Final 9/17/2021 No Access for Inspection GREGG CUMMINGS
Green Building Final 9/17/2021 No Access for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 9/17/2021 No Access for Inspection GREGG CUMMINGS
Final 1/20/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 1/20/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 1/20/2022 Approved GREGG CUMMINGS
Final 1/27/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 1/27/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 2/1/2022 Approved GREGG CUMMINGS
Final 2/1/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 2/1/2022 Approved GREGG CUMMINGS
PLUMBING-Final 2/1/2022 Approved GREGG CUMMINGS