1628 S GARTH AVE 90035

Certificate Information: 1628 S GARTH AVE 90035

Application / Permit
20014-20000-02275
Plan Check / Job No.
B20VN07387
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
9'-5" X 21'-0" ADDITION TO AND CONVERT 12' X 16' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ENGINEER
Permit Issued
Issued on 9/1/2020
Issuing Office
Current Status
CofO Issued on 6/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 RARES BODEA
Corrections Issued 6/11/2020 RARES BODEA
Plan Check Approved 7/30/2020 JEROME MAGAT PALMA
Issued 9/1/2020 APPLICANT
Building Plans Picked Up 9/14/2020 APPLICANT
CofO in Progress 6/7/2025 MICHAEL PELHAM
Permit Finaled 6/7/2025 RICHARD STEINBACH
CofO Issued 6/7/2025 RICHARD STEINBACH
Permit Finaled 6/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/9/2020 RENZ SORIANO
Address approval Cleared 7/10/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/10/2020 RENZ SORIANO
Sewer availability Cleared 7/10/2020 RENZ SORIANO

Contact Information

Contractor F S General Builders Corp; Lic. No.: 1046177-B 17029 COOLFIELD DRIVE      COVINA, CA 91722
Engineer Segovia,, Felipe; Lic. No.: C41102 2320 SANTA CRUZ CT      TORRANCE, CA 90501

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2020 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/21/2020 Corrections Issued EVAN COOPER
Deputy Drilled-In Anchors 10/6/2020 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 10/8/2020 Approved EVAN COOPER
PLUMBING-Rough 10/8/2020 Partial Approval EVAN COOPER
Sewer 10/8/2020 Approved EVAN COOPER
ELECTRICAL-Rough 11/16/2020 Corrections Issued EVAN COOPER
HVAC-Rough 11/16/2020 Corrections Issued EVAN COOPER
PLUMBING-Rough 11/16/2020 Corrections Issued EVAN COOPER
Wood Frame 11/16/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 11/23/2020 Partial Approval EVAN COOPER
Rough-Elec/Plmb/HVAC 11/23/2020 Approved EVAN COOPER
Insulation 11/30/2020 Approved EVAN COOPER
Interior/Exterior Lathing 11/30/2020 Approved EVAN COOPER
Drywall Nailing 12/7/2020 Approved EVAN COOPER
Green Building Rough 12/7/2020 Approved EVAN COOPER
Interior/Exterior Lathing 12/7/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 3/25/2021 Not Ready for Inspection PIERRE VEGA
Final 3/25/2021 No Access for Inspection PIERRE VEGA
Footing/Foundation/Slab 3/25/2021 Not Ready for Inspection PIERRE VEGA
Green Building Final 3/25/2021 No Access for Inspection PIERRE VEGA
METHANE-Barrier 3/25/2021 No Access for Inspection PIERRE VEGA
METHANE-Final 3/25/2021 Not Ready for Inspection PIERRE VEGA
METHANE-Rough 3/25/2021 No Access for Inspection PIERRE VEGA
METHANE-Subgrade 3/25/2021 No Access for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 3/25/2021 No Access for Inspection PIERRE VEGA
BUILDING-Rough-Frame 3/31/2021 Approved EVAN COOPER
Final 3/31/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 3/31/2021 Approved EVAN COOPER
Green Building Final 3/31/2021 Not Ready for Inspection EVAN COOPER
METHANE-Barrier 3/31/2021 Approved EVAN COOPER
METHANE-Final 3/31/2021 Approved EVAN COOPER
METHANE-Rough 3/31/2021 Approved EVAN COOPER
METHANE-Subgrade 3/31/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 3/31/2021 Approved EVAN COOPER
Final 4/20/2021 Corrections Issued EVAN COOPER
Green Building Final 4/20/2021 Not Ready for Inspection EVAN COOPER
Final 6/7/2025 OK to Issue CofO MICHAEL PELHAM
Green Building Final 6/7/2025 Approved MICHAEL PELHAM