8262 N LAURELGROVE AVE 91605

Certificate Information: 8262 N LAURELGROVE AVE 91605

Application / Permit
20014-20000-02269
Plan Check / Job No.
B20VN07368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
68'-5" X 37'-10" ADDITION TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL
Permit Issued
Issued on 2/26/2021
Issuing Office
Valley
Current Status
Issued on 2/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 SELLA BENYAMIN
Corrections Issued 7/7/2020 SELLA BENYAMIN
Quality Review Completed 7/8/2020 STEVEN KIM
Building Plans Picked Up 7/9/2020 APPLICANT
Plan Check Approved 2/5/2021 SELLA BENYAMIN
Issued 2/26/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/23/2020 GABRIEL ROBLES
Sewer availability Cleared 7/23/2020 GABRIEL ROBLES
Low Impact Development Cleared 1/13/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/29/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 5/28/2021 Partial Approval MATTHEW NELSON
Green Building Rough 5/28/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 5/28/2021 Partial Approval MATTHEW NELSON
Underground Mechanical 5/28/2021 Not Ready for Inspection MATTHEW NELSON
Pre-Inspection 11/29/2021 Corrections Issued MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 3/16/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/25/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 3/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/25/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 4/4/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 4/4/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 4/4/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/10/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 5/10/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/10/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/17/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/3/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/3/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 10/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 10/3/2022 Approved CHRISTOPHER DELLEFIELD