10925 N WESCOTT AVE 91040

Certificate Information: 10925 N WESCOTT AVE 91040

Application / Permit
20014-20000-02246
Plan Check / Job No.
B20VN07304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRR. SHAPE 25'2" x 22'3" ADDITION TO THE (E) DWELLING FOR LIVING ROOM PER ENGINEERING.
Permit Issued
Issued on 9/9/2020
Issuing Office
Current Status
Issued on 9/9/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 JEFFREY TANGONAN
Corrections Issued 6/4/2020 JEFFREY TANGONAN
Issued 9/9/2020 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/16/2020 BRIAN MILLER
Low Impact Development Cleared 8/28/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 9/1/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 9/1/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/28/2020 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 10/5/2020 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 10/8/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/16/2020 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 10/30/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 10/30/2020 Approved MATTHEW NELSON
Green Building Rough 10/30/2020 Approved MATTHEW NELSON
HVAC-Rough 10/30/2020 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 11/2/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 11/5/2020 Approved MATTHEW NELSON
Insulation 11/5/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/5/2020 Approved MATTHEW NELSON
Drywall Nailing 11/10/2020 Approved BEAU COLLINS
Final 3/5/2021 Corrections Issued MATTHEW NELSON
Green Building Final 3/5/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/5/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/5/2021 Corrections Issued MATTHEW NELSON
Final 11/15/2021 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/15/2021 Approved MICHEL ABAJAN