5255 W GLASGOW WAY 90045

Certificate Information: 5255 W GLASGOW WAY 90045

Application / Permit
20014-20000-02237
Plan Check / Job No.
B20VN07281
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 8'-0" X 15'-2" TO EXTEND (E) MASTER BEDROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
CofO Issued on 5/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/13/2020 ANGELICA DAVE
Corrections Issued 7/13/2020 ANGELICA DAVE
Applicant returned to address corrections 8/12/2020 JENNIFER LEE
Applicant returned to address corrections 9/29/2020 ALFREDO JARA
Applicant returned to address corrections 10/29/2020 RICHARD GARCIA
Plan Check Approved 11/13/2020 JASON JANGADA
Issued 11/19/2020 APPLICANT
CofO in Progress 5/10/2021 BRENDAN LOONEY
CofO Issued 5/26/2021 VINCENT COTTON
Permit Finaled 5/26/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/15/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 9/15/2020 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 11/13/2020 ANGELICA MARTINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2020 Partial Approval JUAN VALENZUELA
METHANE-Barrier 11/30/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 11/30/2020 Approved JUAN VALENZUELA
Footing/Foundation/Slab 12/3/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 12/9/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 2/2/2021 Approved DAVID HEINE
ELECTRICAL-Rough 2/8/2021 Approved ENRIQUE MIRELES
Pre-Inspection 2/8/2021 Approved ENRIQUE MIRELES
Insulation 2/16/2021 Approved DAVID HEINE
Drywall Nailing 2/19/2021 Approved ANTHONY MCDOWALL
Green Building Rough 2/19/2021 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 2/19/2021 Approved ANTHONY MCDOWALL
BUILDING-Rough-Frame 4/30/2021 Approved BRENDAN LOONEY
Final 4/30/2021 Conditional Approval BRENDAN LOONEY
Green Building Final 4/30/2021 Approved BRENDAN LOONEY
METHANE-Final 4/30/2021 Approved BRENDAN LOONEY
METHANE-Rough 4/30/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 4/30/2021 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 4/30/2021 Approved BRENDAN LOONEY
Final 5/6/2021 OK to Issue CofO BRENDAN LOONEY