9374 W MONTE MAR DR 90035

Certificate Information: 9374 W MONTE MAR DR 90035

Application / Permit
20014-20000-02236
Plan Check / Job No.
B20VN07276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE (E) 4'-11" X 9'-11" PORTION OF COVERED PATIO & ENCLOSE 4'-6" X 7'-3" FRONT PORCHAND INTERIOR REMODEL TO THE (E) SFD.
Permit Issued
Issued on 7/31/2020
Issuing Office
Current Status
Permit Finaled on 6/28/2021

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 DAWN MC NULTY
Corrections Issued 6/11/2020 DAWN MC NULTY
Building Plans Picked Up 6/16/2020 APPLICANT
Plan Check Approved 7/13/2020 RAPHAEL ROSAS
Issued 7/31/2020 APPLICANT
Permit Finaled 6/28/2021 KEVIN SARGSYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/1/2020 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Gentjan; Lic. No.: C88031 157 S LOS ROBLES AVE 12      PASADENA, CA 91101

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/4/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 9/4/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/8/2020 Approved KEVIN SARGSYAN
Wood Frame 10/7/2020 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 11/5/2020 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 11/24/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/24/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 12/4/2020 Approved KEVIN SARGSYAN
Insulation 12/11/2020 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Approved KEVIN SARGSYAN
HVAC-Rough 1/25/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/25/2021 Approved KEVIN SARGSYAN
HVAC-Rough 2/8/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/8/2021 Partial Approval KEVIN SARGSYAN
Shower Pan 2/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 2/9/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/23/2021 Approved KEVIN SARGSYAN
Wood Frame 3/8/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 3/10/2021 Approved KEVIN SARGSYAN
Green Building Rough 3/10/2021 Approved KEVIN SARGSYAN
METHANE-Rough 3/10/2021 Approved KEVIN SARGSYAN
Insulation 3/11/2021 Approved KENNETH NAGLE
Drywall Nailing 3/18/2021 Approved KEVIN SARGSYAN
Final 6/14/2021 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/14/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 6/14/2021 Approved KEVIN SARGSYAN
Final 6/28/2021 Permit Finaled KEVIN SARGSYAN