174 S GREENFIELD AVE 90049
Certificate Information: 174 S GREENFIELD AVE 90049
- Application / Permit
- 20014-20000-02226
- Plan Check / Job No.
- B20VN07237
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 21'6" X 20' ADDITON OF A 2 CAR GARAGE TO (E) SFD ,NEW 24'10" X 4' FRONT PORCH NEW 69'4" X 66'8" ADDITION TO (E) SFD TO RELOCATE AND REMODEL KITCHEN AND DINING ROOM , ADD (2) BEDROOMS , RELOCATE LAUNDRY ROOM , ADD POWDER ROOM , MAJOR REMODEL TO (E) SFD TO REMODEL (3) BEDROOMS , FAMILY ROOM , REMODEL (2) BATHROOMS, CREATE (2) BATHROOMS, RE-FERAME ALL THE ROOF, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING- SEE COMMNENTS
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | RARES BODEA |
| Corrections Issued | 7/7/2020 | RARES BODEA |
| Quality Review Completed | 7/8/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 12/13/2021 | RARES BODEA |
| Applicant returned to address corrections | 12/14/2021 | RARES BODEA |
| Applicant returned to address corrections | 1/21/2022 | RARES BODEA |
| Plan Check Approved | 1/27/2022 | RARES BODEA |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 2/15/2025 | MICHAEL PELHAM |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
| CofO Issued | 2/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Watercourse | Cleared | 7/30/2020 | MAHELET GEBEYHU |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 3/30/2021 | ANTHONY MAINEZ |
| Permit | Cleared | 4/5/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 4/24/2021 | KURT CORRAL |
| Trees in Parkway | Cleared | 6/2/2021 | JOHN KIM |
| Low Impact Development | Cleared | 12/7/2021 | TA ANH |
| GPI Written Notices | Cleared | 12/18/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 12/18/2021 | RARES BODEA |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/19/2022 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/28/2022 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/12/2022 | No Access for Inspection | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 5/12/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 5/12/2022 | No Access for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/12/2022 | No Access for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 5/12/2022 | No Access for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/16/2022 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 5/16/2022 | Approved | CARLOS MATAMOROS |
| Wood Frame | 5/16/2022 | Conditional Approval | CARLOS MATAMOROS |
| Insulation | 5/20/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 5/25/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 5/25/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 5/25/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 6/17/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 12/28/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Wood Construction | 12/29/2022 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/12/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 1/12/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 1/12/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/12/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/12/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 1/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/2/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 2/2/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 2/2/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/2/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/2/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/9/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/21/2023 | No Access for Inspection | CARLOS MATAMOROS |
| Shower Pan | 3/31/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/14/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 8/17/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/11/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 1/11/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/22/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 1/22/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 1/22/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/22/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Smoke Detectors | 1/22/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| Final | 2/3/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 2/3/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 2/3/2025 | Approved | CARLOS MATAMOROS |
| Final | 2/15/2025 | OK to Issue CofO | MICHAEL PELHAM |