11443 N ODESSA AVE 91344

Certificate Information: 11443 N ODESSA AVE 91344

Application / Permit
20014-20000-02221
Plan Check / Job No.
B20VN07227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18'-3" X 20'-3" (E) DETACHED GARAGE AND ADD IRREGULAR SHAPE (15' X 22') TO CREATE (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 8/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 SEAN SHAHMIRI
Corrections Issued 6/5/2020 SEAN SHAHMIRI
Building Plans Picked Up 6/9/2020 APPLICANT
Issued 8/17/2020 APPLICANT
CofO in Progress 1/6/2023 JAVIER RAMOS JR
CofO in Progress 1/19/2023 ROBERT GOLD
Permit Finaled 1/21/2023 MICHAEL SMITH
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/25/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 6/25/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 6/26/2020 GUILLERMO PETRA
Sewer availability Cleared 6/26/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2020 Corrections Issued MARK JOHNSON
Excavation/Setback/Form/Re-Bar 10/9/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/24/2020 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 11/24/2020 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval MARK JOHNSON
Green Building Rough 11/24/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 11/24/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 11/24/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/16/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 12/16/2020 Approved MARK JOHNSON
Green Building Rough 12/16/2020 Approved MARK JOHNSON
HVAC-Rough 12/16/2020 Approved MARK JOHNSON
Insulation 12/28/2020 Approved MARK JOHNSON
Shower Pan 12/28/2020 Not Ready for Inspection MARK JOHNSON
Drywall Nailing 1/4/2021 Approved MARK JOHNSON
Sewer 1/21/2021 Approved MICHAEL TEMPLE
Underground Mechanical 1/21/2021 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Final 10/25/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Final 10/25/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Final 10/25/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Final 4/8/2022 Corrections Issued RAUL OLAGI
Final 4/8/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 4/8/2022 Approved RAUL OLAGI
Green Building Final 4/8/2022 Corrections Issued RAUL OLAGI
HVAC-Final 4/8/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 4/8/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 4/8/2022 Approved RAUL OLAGI
ELECTRICAL-Final 6/10/2022 Approved JAVIER RAMOS JR
Final 6/10/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 6/10/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 6/10/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 6/10/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved JAVIER RAMOS JR
Final 9/15/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 9/15/2022 Approved JAVIER RAMOS JR
HVAC-Final 9/15/2022 Approved JAVIER RAMOS JR