5030 N DEL MORENO DR 91364
Certificate Information: 5030 N DEL MORENO DR 91364
- Application / Permit
- 20014-20000-02214
- Plan Check / Job No.
- B20VN07181
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 9'-0" X 5'-7" PORTION OF (E) ATTACHED GARAGE TO ENLARGE BEDROOM. REMOVE WALLS BETWEEN KITCHEN, DINING ROOM, AND FAMILY ROOM. REMOVE AND REPLACE DOORS AND WINDOWS THROUGHOUT DWELLING. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 11/5/2020
- Issuing Office
- Current Status
- CofO Issued on 7/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 6/22/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 6/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 6/26/2020 | APPLICANT |
| Plan Check Approved | 9/22/2020 | JEROME MAGAT PALMA |
| Issued | 11/5/2020 | APPLICANT |
| CofO in Progress | 7/7/2021 | PETER FOLLING |
| CofO in Progress | 7/7/2021 | PETER FOLLING |
| Permit Finaled | 7/24/2021 | MICHAEL SMITH |
| CofO Issued | 7/24/2021 | MICHAEL SMITH |
| Permit Finaled | 7/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 8/17/2020 | PABLO ESTRADA |
| Grading Pre-Inspection | Cleared | 9/28/2020 | BARTON HOLMES |
Contact Information
| Contractor | Krumm Mike Construction Inc; Lic. No.: 915844-B | 613 ONDA DRIVE CAMARILLO, CA 93010 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2020 | Conditional Approval | DONALD SUNSERI |
| Footing/Foundation/Slab | 1/12/2021 | Approved | PAUL CHOPP |
| BUILDING-Rough-Frame | 3/11/2021 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/11/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 3/11/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 3/11/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/11/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 3/11/2021 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/16/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/16/2021 | Approved | TROY SANDERS |
| Green Building Rough | 3/16/2021 | Approved | TROY SANDERS |
| Insulation | 3/16/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/16/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 3/16/2021 | Approved | TROY SANDERS |
| Shower Pan | 3/16/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 3/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/22/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/17/2021 | Approved | PETER FOLLING |
| Final | 6/17/2021 | OK to Issue CofO | PETER FOLLING |
| Green Building Final | 6/17/2021 | Approved | PETER FOLLING |
| HVAC-Final | 6/17/2021 | Approved | PETER FOLLING |
| PLUMBING-Final | 6/17/2021 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/17/2021 | SGSOV Gas Company | PETER FOLLING |
| Smoke Detectors | 6/17/2021 | Approved | PETER FOLLING |