13167 W FILMORE ST 91331
Certificate Information: 13167 W FILMORE ST 91331
- Application / Permit
- 20014-20000-02206
- Plan Check / Job No.
- B20VN07151
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION & CONVERT (E) REC. RM. INTO 2-STORY ADU PER LAMC 12.22 A.33(c) AND (d) COMPLY WITH DEPARTMENT ORDER effective date 07/30/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- Issued on 9/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | JESSE ARELLANO |
| Corrections Issued | 7/25/2020 | JESSE ARELLANO |
| Quality Review Completed | 7/27/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/14/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/28/2021 | JESSE ARELLANO |
| Plan Check Approved | 9/12/2021 | JESSE ARELLANO |
| Issued | 9/13/2021 | APPLICANT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/5/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/11/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 5/14/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/8/2023 | Corrections Issued | PIERRE VEGA |
| Underground Mechanical | 8/24/2023 | Approved | PIERRE VEGA |
| Deputy Drilled-In Anchors | 11/3/2023 | No Result Entered | MARSHALL RUMPF |
| Footing/Foundation/Slab | 11/9/2023 | No Access for Inspection | PIERRE VEGA |
| METHANE-Barrier | 11/9/2023 | No Access for Inspection | PIERRE VEGA |
| METHANE-Subgrade | 11/9/2023 | No Access for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 11/17/2023 | Corrections Issued | MARK VAN SLOOTEN |
| METHANE-Barrier | 11/17/2023 | Corrections Issued | MARK VAN SLOOTEN |
| METHANE-Subgrade | 11/17/2023 | Corrections Issued | MARK VAN SLOOTEN |
| Deputy Drilled-In Anchors | 2/26/2024 | Approved | MARK VAN SLOOTEN |
| Footing/Foundation/Slab | 2/26/2024 | Corrections Issued | MARK VAN SLOOTEN |
| METHANE-Barrier | 2/26/2024 | Approved | MARK VAN SLOOTEN |
| METHANE-Rough | 2/26/2024 | Approved | MARK VAN SLOOTEN |
| METHANE-Subgrade | 2/26/2024 | Approved | MARK VAN SLOOTEN |
| Footing/Foundation/Slab | 5/7/2024 | Approved | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 10/30/2024 | Partial Approval | MARK VAN SLOOTEN |
| Green Building Rough | 10/30/2024 | Approved | MARK VAN SLOOTEN |
| Deputy Drilled-In Anchors | 12/17/2024 | Approved | RAUL VASQUEZ |
| Deputy Wood Construction | 12/17/2024 | Approved | RAUL VASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Approved | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 10/6/2025 | Corrections Issued | RAUL VASQUEZ |
| ELECTRICAL-Rough | 10/6/2025 | Approved | RAUL VASQUEZ |
| HVAC-Rough | 10/6/2025 | Corrections Issued | RAUL VASQUEZ |
| Interior/Exterior Lathing | 10/6/2025 | Approved | RAUL VASQUEZ |
| PLUMBING-Rough | 10/6/2025 | Approved | RAUL VASQUEZ |
| Insulation | 10/31/2025 | Approved | MARK VAN SLOOTEN |
| Drywall Nailing | 12/5/2025 | Approved | MARK VAN SLOOTEN |
| Service/Power Release | 3/2/2026 | Corrections Issued | MARK VAN SLOOTEN |
| Shower Pan | 3/2/2026 | Approved | MARK VAN SLOOTEN |