13167 W FILMORE ST 91331

Certificate Information: 13167 W FILMORE ST 91331

Application / Permit
20014-20000-02206
Plan Check / Job No.
B20VN07151
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION & CONVERT (E) REC. RM. INTO 2-STORY ADU PER LAMC 12.22 A.33(c) AND (d) COMPLY WITH DEPARTMENT ORDER effective date 07/30/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/13/2021
Issuing Office
Current Status
Issued on 9/13/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 JESSE ARELLANO
Corrections Issued 7/25/2020 JESSE ARELLANO
Quality Review Completed 7/27/2020 OMID HEDAYAT
Applicant returned to address corrections 5/14/2021 JESSE ARELLANO
Applicant returned to address corrections 6/28/2021 JESSE ARELLANO
Plan Check Approved 9/12/2021 JESSE ARELLANO
Issued 9/13/2021 APPLICANT
Building Plans Picked Up 9/14/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/5/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/5/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/11/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Green Code Cleared 5/14/2021 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/8/2023 Corrections Issued PIERRE VEGA
Underground Mechanical 8/24/2023 Approved PIERRE VEGA
Deputy Drilled-In Anchors 11/3/2023 No Result Entered MARSHALL RUMPF
Footing/Foundation/Slab 11/9/2023 No Access for Inspection PIERRE VEGA
METHANE-Barrier 11/9/2023 No Access for Inspection PIERRE VEGA
METHANE-Subgrade 11/9/2023 No Access for Inspection PIERRE VEGA
Footing/Foundation/Slab 11/17/2023 Corrections Issued MARK VAN SLOOTEN
METHANE-Barrier 11/17/2023 Corrections Issued MARK VAN SLOOTEN
METHANE-Subgrade 11/17/2023 Corrections Issued MARK VAN SLOOTEN
Deputy Drilled-In Anchors 2/26/2024 Approved MARK VAN SLOOTEN
Footing/Foundation/Slab 2/26/2024 Corrections Issued MARK VAN SLOOTEN
METHANE-Barrier 2/26/2024 Approved MARK VAN SLOOTEN
METHANE-Rough 2/26/2024 Approved MARK VAN SLOOTEN
METHANE-Subgrade 2/26/2024 Approved MARK VAN SLOOTEN
Footing/Foundation/Slab 5/7/2024 Approved MARK VAN SLOOTEN
BUILDING-Rough-Frame 10/30/2024 Partial Approval MARK VAN SLOOTEN
Green Building Rough 10/30/2024 Approved MARK VAN SLOOTEN
Deputy Drilled-In Anchors 12/17/2024 Approved RAUL VASQUEZ
Deputy Wood Construction 12/17/2024 Approved RAUL VASQUEZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Approved MARK VAN SLOOTEN
BUILDING-Rough-Frame 10/6/2025 Corrections Issued RAUL VASQUEZ
ELECTRICAL-Rough 10/6/2025 Approved RAUL VASQUEZ
HVAC-Rough 10/6/2025 Corrections Issued RAUL VASQUEZ
Interior/Exterior Lathing 10/6/2025 Approved RAUL VASQUEZ
PLUMBING-Rough 10/6/2025 Approved RAUL VASQUEZ
Insulation 10/31/2025 Approved MARK VAN SLOOTEN
Drywall Nailing 12/5/2025 Approved MARK VAN SLOOTEN
Service/Power Release 3/2/2026 Corrections Issued MARK VAN SLOOTEN
Shower Pan 3/2/2026 Approved MARK VAN SLOOTEN