1210 W 80TH ST 90044
Certificate Information: 1210 W 80TH ST 90044
- Application / Permit
- 20014-20000-02204
- Plan Check / Job No.
- B20VN07143
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 2ND FLOOR BY CONVERTING PORTION OF (E) ATTIC AREA (55.7 sf) TO (N) STORAGE ROOM AND INTERIOR REMODEL OF (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 9/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | SEAN SHAHMIRI |
| Corrections Issued | 6/20/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 7/14/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/14/2020 | APPLICANT |
| Green Plans Picked Up | 7/14/2020 | APPLICANT |
| Plan Check Approved | 9/2/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/14/2020 | SEAN SHAHMIRI |
| Issued | 9/17/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | HORACE FULTZ |
| Permit Finaled | 9/20/2021 | DEROLD HAUFF |
| CofO Issued | 9/20/2021 | DEROLD HAUFF |
| Permit Finaled | 9/20/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 7/22/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 7/22/2020 | RENZ SORIANO |
| ZA Case | Cleared | 8/18/2020 | STEVEN WECHSLER |
| ZI | Cleared | 8/26/2020 | RAFAEL FONTES |
Contact Information
| Contractor | Golden Age Builders; Lic. No.: 1040171-B | 1411 N HIGHLAND AVE #518 LOS ANGELES, CA 90028 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/27/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/27/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/27/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 4/27/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 4/27/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/27/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/11/2021 | Approved | EUGENE CASSIDY |
| Insulation | 5/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/20/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Shower Pan | 5/20/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/26/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 5/26/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 5/26/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 6/7/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/7/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 6/7/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/15/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/15/2021 | Approved | EUGENE CASSIDY |
| Insulation | 6/22/2021 | Approved | JESUS PINEDA |
| Shower Pan | 6/22/2021 | Approved | JESUS PINEDA |
| Drywall Nailing | 6/29/2021 | Approved | HORACE FULTZ |
| Final | 8/26/2021 | OK to Issue CofO | HORACE FULTZ |
| Green Building Final | 8/26/2021 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 8/26/2021 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 8/26/2021 | Approved | HORACE FULTZ |