15202 W MARTHA ST 91411

Certificate Information: 15202 W MARTHA ST 91411

Application / Permit
20014-20000-02197
Plan Check / Job No.
B20VN07111
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-10" X 20' GARAGE AND ADD 12'-5" X 18'-10" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 8/28/2020
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 NILOOFAR MEHRAIN
Corrections Issued 6/4/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 6/5/2020 APPLICANT
Applicant returned to address corrections 7/31/2020 RAPHAEL ROSAS
Applicant returned to address corrections 8/18/2020 JENNIFER LEE
Plan Check Approved 8/28/2020 OMAR GARNICA
Issued 8/28/2020 APPLICANT
CofO in Progress 9/30/2025 RYAN SALAZAR
Permit Finaled 10/7/2025 RUBEN SALAS
CofO Issued 10/7/2025 RUBEN SALAS
Permit Finaled 10/7/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 6/6/2020 WALTER RAMIREZ
Construction within easement Cleared 6/6/2020 WALTER RAMIREZ
CPC Cleared 6/8/2020 HERMINIGILDO AGUSTIN
ZI Cleared 6/8/2020 HERMINIGILDO AGUSTIN
Address approval Cleared 6/9/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/9/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/9/2020 ADRIAN CASTRO
Sewer availability Cleared 6/9/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 6/25/2020 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/21/2020 Partial Approval DANIEL ORRANTE
Footing/Foundation/Slab 10/23/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/16/2021 Corrections Issued MICHAEL TEMPLE
Green Building Rough 4/16/2021 Not Ready for Inspection MICHAEL TEMPLE
Rough-Elec/Plmb/HVAC 4/16/2021 Not Ready for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 7/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 7/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 7/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
HVAC-Rough 7/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 7/21/2021 Not Ready for Inspection ARTHUR SARGSYAN
Pre-Inspection 11/21/2022 Partial Inspection ROBERT GOLD
BUILDING-Rough-Frame 11/23/2022 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 11/23/2022 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 11/23/2022 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 11/23/2022 Approved JOHN COLEMAN
PLUMBING-Rough 11/23/2022 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 1/24/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/24/2023 Approved RYAN SALAZAR
Green Building Rough 1/24/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 1/24/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/27/2023 Approved WILLIAM WREN
Insulation 1/30/2023 Approved RYAN SALAZAR
Drywall Nailing 2/6/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/6/2023 Approved RYAN SALAZAR
PLUMBING-Rough 6/6/2023 Corrections Issued RYAN SALAZAR
Sewer 6/6/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 8/26/2025 Approved RYAN SALAZAR
Final 8/26/2025 Corrections Issued RYAN SALAZAR
Green Building Final 8/26/2025 Approved RYAN SALAZAR
Green Building Rough 8/26/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/26/2025 Approved RYAN SALAZAR
Special/Order Compliance 9/11/2025 Not Ready for Inspection RYAN SALAZAR
Final 9/29/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 9/29/2025 Approved RYAN SALAZAR