14614 1/2 W VOSE ST 91405

Certificate Information: 14614 1/2 W VOSE ST 91405

Application / Permit
20014-20000-02178
Plan Check / Job No.
B20VN07079
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
27'-0" X 38'-2" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (1197 SQ FT).
Permit Issued
Issued on 12/15/2020
Issuing Office
Current Status
CofO Issued on 10/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 JEROME MAGAT PALMA
Corrections Issued 6/27/2020 JEROME MAGAT PALMA
Quality Review Completed 7/8/2020 STEVEN KIM
Building Plans Picked Up 7/9/2020 APPLICANT
Plan Check Approved 12/15/2020 JEROME MAGAT PALMA
Issued 12/15/2020 APPLICANT
CofO in Progress 10/17/2021 JENNIFER RABUCHIN
Permit Finaled 10/18/2021 MICHAEL SMITH
CofO Issued 10/18/2021 MICHAEL SMITH
Permit Finaled 10/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/12/2020 ADRIAN CASTRO
Low Impact Development Cleared 11/16/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 11/24/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/24/2020 ADRIAN CASTRO
Sewer availability Cleared 11/24/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/2/2020 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/21/2020 Partial Approval BEAU COLLINS
Sewer 12/21/2020 Partial Approval BEAU COLLINS
Excavation/Setback/Form/Re-Bar 1/8/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 1/13/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/14/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 3/2/2021 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Partial Approval JOHN HAYES
PLUMBING-Rough 3/2/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 3/2/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 3/9/2021 Approved JOHN STEPHENS
ELECTRICAL-Rough 3/26/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 4/5/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Approved MICHEL ABAJAN
Green Building Rough 4/5/2021 Approved MICHEL ABAJAN
HVAC-Rough 4/5/2021 Approved MICHEL ABAJAN
Insulation 4/14/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/14/2021 Partial Approval MISAEL ESPARZA
Shower Pan 4/14/2021 Approved MISAEL ESPARZA
Insulation 4/20/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 4/20/2021 Partial Approval CHARLES POWELL
Shower Pan 4/20/2021 Approved CHARLES POWELL
Drywall Nailing 4/27/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 4/27/2021 Approved KRISTEN CAUSEY
Pre-Inspection 4/27/2021 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Final 7/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 7/1/2021 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 7/1/2021 Approved ARTHUR SARGSYAN
Gas Test 7/1/2021 Approved ARTHUR SARGSYAN
Green Building Final 7/1/2021 Approved ARTHUR SARGSYAN
HVAC-Final 7/1/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 7/1/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/1/2021 SGSOV Approved ARTHUR SARGSYAN
Service/Power Release 7/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
Smoke Detectors 7/1/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 8/11/2021 Approved JENNIFER RABUCHIN
Final 8/11/2021 Partial Approval JENNIFER RABUCHIN
Green Building Final 8/11/2021 Approved JENNIFER RABUCHIN
Service/Power Release 8/11/2021 Approved JENNIFER RABUCHIN
Final 10/18/2021 OK to Issue CofO JENNIFER RABUCHIN