14614 1/2 W VOSE ST 91405
Certificate Information: 14614 1/2 W VOSE ST 91405
- Application / Permit
- 20014-20000-02178
- Plan Check / Job No.
- B20VN07079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 27'-0" X 38'-2" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (1197 SQ FT).
- Permit Issued
- Issued on 12/15/2020
- Issuing Office
- Current Status
- CofO Issued on 10/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 6/27/2020 | JEROME MAGAT PALMA |
| Quality Review Completed | 7/8/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Plan Check Approved | 12/15/2020 | JEROME MAGAT PALMA |
| Issued | 12/15/2020 | APPLICANT |
| CofO in Progress | 10/17/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 10/18/2021 | MICHAEL SMITH |
| CofO Issued | 10/18/2021 | MICHAEL SMITH |
| Permit Finaled | 10/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 11/16/2020 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/24/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/2/2020 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/21/2020 | Partial Approval | BEAU COLLINS |
| Sewer | 12/21/2020 | Partial Approval | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/13/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/14/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 3/2/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 3/2/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/2/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/9/2021 | Approved | JOHN STEPHENS |
| ELECTRICAL-Rough | 3/26/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/5/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/5/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/5/2021 | Approved | MICHEL ABAJAN |
| Insulation | 4/14/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/14/2021 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 4/14/2021 | Approved | MISAEL ESPARZA |
| Insulation | 4/20/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 4/20/2021 | Partial Approval | CHARLES POWELL |
| Shower Pan | 4/20/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 4/27/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 4/27/2021 | Approved | KRISTEN CAUSEY |
| Pre-Inspection | 4/27/2021 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 7/1/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| Gas Test | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 7/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Smoke Detectors | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 8/11/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/11/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 8/11/2021 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/11/2021 | Approved | JENNIFER RABUCHIN |
| Final | 10/18/2021 | OK to Issue CofO | JENNIFER RABUCHIN |