10337 N CEDROS AVE 91345
Certificate Information: 10337 N CEDROS AVE 91345
- Application / Permit
- 20014-20000-02163
- Plan Check / Job No.
- B20VN07026
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 31' X 39'-2" ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 3/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | SERGIO MUNIZ |
| Corrections Issued | 6/18/2020 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/19/2020 | APPLICANT |
| Applicant returned to address corrections | 9/2/2020 | SERGIO MUNIZ |
| Plan Check Approved | 9/11/2020 | SERGIO MUNIZ |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 12/9/2021 | JENNIFER RABUCHIN |
| No Progress | 1/17/2022 | MICHAEL TEMPLE |
| CofO in Progress | 3/5/2022 | MICHAEL TEMPLE |
| Permit Finaled | 3/16/2022 | RONALD MYRICK |
| CofO Issued | 3/16/2022 | RONALD MYRICK |
| Permit Finaled | 3/16/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/12/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/14/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/19/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/6/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/22/2021 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 4/22/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 4/28/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/24/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/4/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/4/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/4/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/4/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/4/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/9/2021 | Not Ready for Inspection | KRISTEN CAUSEY |
| Insulation | 6/17/2021 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/17/2021 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 6/22/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/25/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/7/2021 | Approved | JENNIFER RABUCHIN |
| Final | 9/27/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 9/27/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 9/27/2021 | Approved | MARK JOHNSON |
| Final | 10/28/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/9/2021 | Approved | JENNIFER RABUCHIN |
| Final | 12/9/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 12/9/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/9/2021 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 1/18/2022 | Partial Inspection | JENNIFER RABUCHIN |