10337 N CEDROS AVE 91345

Certificate Information: 10337 N CEDROS AVE 91345

Application / Permit
20014-20000-02163
Plan Check / Job No.
B20VN07026
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
31' X 39'-2" ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2020 APPLICANT
Assigned to Plan Check Engineer 6/17/2020 SERGIO MUNIZ
Corrections Issued 6/18/2020 SERGIO MUNIZ
Building Plans Picked Up 6/19/2020 APPLICANT
Applicant returned to address corrections 9/2/2020 SERGIO MUNIZ
Plan Check Approved 9/11/2020 SERGIO MUNIZ
Issued 12/9/2020 APPLICANT
CofO in Progress 12/9/2021 JENNIFER RABUCHIN
No Progress 1/17/2022 MICHAEL TEMPLE
CofO in Progress 3/5/2022 MICHAEL TEMPLE
Permit Finaled 3/16/2022 RONALD MYRICK
CofO Issued 3/16/2022 RONALD MYRICK
Permit Finaled 3/16/2022 RONALD MYRICK

Permit Application Clearance Information

Low Impact Development Cleared 8/12/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/14/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/17/2020 GUILLERMO PETRA
Sewer availability Cleared 8/19/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 4/6/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/22/2021 Partial Approval JENNIFER RABUCHIN
Wood Frame 4/22/2021 Partial Approval JENNIFER RABUCHIN
Insulation 4/28/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/24/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/4/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/4/2021 Approved JENNIFER RABUCHIN
Green Building Rough 6/4/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 6/4/2021 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 6/4/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/4/2021 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 6/9/2021 Not Ready for Inspection KRISTEN CAUSEY
Insulation 6/17/2021 Approved JAVIER RAMOS JR
Shower Pan 6/17/2021 Corrections Issued JAVIER RAMOS JR
Shower Pan 6/22/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 6/25/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/7/2021 Approved JENNIFER RABUCHIN
Final 9/27/2021 Corrections Issued MARK JOHNSON
Green Building Final 9/27/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 9/27/2021 Approved MARK JOHNSON
Final 10/28/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Final 12/9/2021 Approved JENNIFER RABUCHIN
Final 12/9/2021 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/9/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/9/2021 Approved JENNIFER RABUCHIN
Pre-Inspection 1/18/2022 Partial Inspection JENNIFER RABUCHIN